Coal shortage sparks jitters in metals sector

The captive producers said they are receiving 15-20% less than the committed quantity of the raw material

coal
Megha Manchanda New Delhi
Last Updated : Dec 16 2017 | 8:31 PM IST
Production in the metals sector has taken a hit as the captive power plants supplying power to the sector are forced to run at 50 per cent capacity due to coal shortage.

Indian captive power producers' association said that the state-owned Coal India was not honouring the fuel supply agreements (FSA) for supplying coal. 

Captive power plants (CPPs) have an installed capacity of about 40,000 MW and require 190 million tonnes of coal annually. As much as 3.6 million tonnes of coal is pending with the Coal India. The captive producers have said that they receiving 15-20 per cent less than the committed quantity of the raw material. 

They are getting average 50 per cent coal against secured linkages and Annual Contracted Quantity. Captive power industry that has a debt of $30 billion is only able to service 50-70 per cent of it. The coal dispatch to CPPs has been affected since April 2017. During this period, even though the coal was available, the captive units were not allotted rakes and the independent power producers (IPPs) were preferred on dispatches. 

The captive producers are suffering huge financial pressure because of the Coal India subsidiaries taking advance payment and bank guarantee against the allotment of coal but not dispatching as per allotment, blocking CPPs funds for six-nine months. 

"Most of the CPP based industries are facing severe coal shortage and struggling even to maintain critical stock level. Reduced power generation is rendering operations economically unviable with huge risk plant closure," Rahul Sharma, Chairman, Indian captive power producers' association said. 

The metals industry is currently relying on imported coal and spot power market to meet its electricity demand. For the aluminum industry energy cost comprises 40 per cent of the total cost of production, as a result of coal shortage the production expenditure has gone up by $300 per tonne.
SUPPLY CONCERNS
Indian captive power producers’ association says Coal India is not honouring fuel supply pacts
Captive power plants have an installed capacity of about 40,000 Mw
The captive power industry has a debt of $30 billion

One subscription. Two world-class reads.

Already subscribed? Log in

Subscribe to read the full story →
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

Next Story