IAF laments HAL delays in delivery of intermediate trainer

Image
Ajai Shukla New Delhi
Last Updated : Feb 06 2013 | 7:28 AM IST

 

The Indian Air Force (IAF) continues to grapple with difficulties in training its pilots. While quality basic training will become possible as the Pilatus Aircraft Company delivers the 75 PC-7 Mark II basic trainers that India bought last year for Rs 2,900 crore, the next stage of training remains an issue. IAF officials say the failure of Hindustan Aeronautics Ltd (HAL) to develop an Intermediate Jet Trainer (IJT) is now a serious hurdle to training.

 

HAL has been developing an IJT, called the Sitara, since 1999. The IAF has forked out R&D costs of Rs 600 crore (up from an initial estimate of Rs 180 crore), and assured HAL of an order of 12 prototypes and 73 operational trainers. But, with the IJT delayed by almost a decade and still at least three years from delivery, rookie pilots will continue to train on outdated and inadequate aircraft.

The IAF trains its fighter pilots in three phases. Stage-1 training will now be carried out on the propeller-driven Pilatus PC-7 Mark II. From there, pilots graduate to Stage-2 training on jet aircraft, which is currently carried out on the vintage Kiran Mark I since the IJT Sitara, which was supposed to replace the Kiran long ago, has not been delivered. Finally, pilots carry out Stage-3 training on the vaunted Hawk Advanced Jet Trainer (AJT), which was acquired in the mid-2000s.

“The IJT has been a very poorly planned programme by HAL and a decade-long delay is unacceptable in a trainer aircraft. Given how much time and money the IAF has already committed, we have to stick with the IJT programme and induct it into service as a Stage-2 trainer,” a top IAF official bitterly complained.

But patience is running out in Vayu Bhawan, the IAF headquarters. A senior air marshal told Business Standard that, if the IJT was not delivered within three years, the IAF would consider using the Pilatus PC-7 Mark II as a Stage-2 trainer, in addition to its primary job as a Stage-1 trainer.

“The Pilatus could also be used for Stage-2 training until the IJT is ready. This could be done using the same aircraft, by putting the trainee pilots through more complex flying exercises,” explains the IAF official.

The IAF brass believes that HAL made a major blunder in deciding to change the IJT’s engine, replacing the French Larzac engine around which the Sitara was designed, with a more powerful AL-55I engine built by Russian engine-maker, NPO-Saturn. In 2005, HAL signed a $350 million contract with Russian defence export agency, Rosoboronexport, to build 250 AL-55I engines under license in Bangalore, with an option for 1000 more. After developing the engine, Moscow insisted on payment of another $64 million.

“HAL should never have gone in for a new engine mid-way, because an aircraft is always designed around its engine. Instead, they should have upgraded the Larzac,” points out a top IAF planner.

Contacted for comments, HAL has not responded. According to engineers involved in the IJT’s development, the testing regime that governs the new Russian engine has delayed the flight-testing of the IJT. This was predictable, since any new engine requires extensive and progressive testing. In this, the Russian certification agency allows the engine to fly only a fixed number of hours, after which the agency examines the engine and then clears it to fly a small number of additional hours. This progressive certification often holds up flight-testing.

Business Standard has followed the IJT Sitara’s development since the early 2000s, on regular visits to HAL. Design began in 1999, and the aircraft flew in 2003, a remarkably quick development process. But then, the engine was changed and problems began. Last year, an IJT prototype crashed, fortunately without loss of life.

HAL has said that it intends to build the IJT in its Kanpur facility, at a cost of about Rs 50 crore per aircraft.

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Feb 05 2013 | 12:35 AM IST

Next Story