To centralise process by setting up special units in each state
The government plans to halve the time it takes to acquire land for road projects, a move that is expected to help it and construction companies save over Rs 10,000 crore, Union Road Transport and Highways Minister Kamal Nath said.
In an interview to Business Standard, Nath said the focus would be on eliminating the many “unnecessary procedures involved” in the land acquisition process.
National Highways Authority of India officials said land acquisition typically takes 24 months, and the plan is to pare that time to 11 months. This will help reduce the time taken for building a road — a process that currently takes five years from conception, design, identifying land, acquiring it and calling for bids once 80 per cent of the land is available.
State administrations are currently responsible for acquiring land for road projects. To streamline the process, NHAI is setting up special land acquisition units all over the country under the responsibility of state government officials on deputation to the authority.
Ten such units are coming up in Rajasthan, 13 in Bihar, 25 in Uttar Pradesh, seven in Gujarat, 11 in Orissa, 13 in West Bengal, four in Jharkhand, 11 in Maharashtra and five in Assam. Around 40 are already operational in Tamil Nadu and Karnataka and sanction has been received for Goa.
These units will be headed by an Additional District Magistrate (ADM) or Sub-Divisional Magistrate (SDM) who will report to the NHAI through project directors (who are NHAI officials appointed to look after the development of the project). The ADM or SDM would be state government officials on deputation to NHAI.
Nath added that other processes would be shortened, such as the practice of translating into Hindi the letters written by project directors to the ministry.
According to a survey, 70 per cent of infrastructure projects in the country are delayed due to land acquisition problems, which include 40 projects by NHAI.
The government has put over 124 road projects worth Rs 100,000 crore up for bidding this year and is expected to offer a similar amount of projects for bidding next year.
The savings as a result of speeding the land acquisition, according to experts, is about 10 per cent of the total project cost.
“Project and construction costs are totally dependent on prices of goods like steel and cement that go into making a road and these prices generally increase every year. Considering 2008 price levels, if the project time is bought down by one year, the construction cost will come down by 15 per cent and the total project cost by 10 per cent,” says Parvesh Minocha, managing director, transport division, Feedback Ventures, an infrastructure services company.
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app