| According to the latest data, the capacity addition of 3,765 Mw in the first seven months of the financial year is just 32 per cent of the target. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| This has led to a further scaling down of expected power capacity addition in the current year from about 17,000 Mw to 12,000 Mw. "We may actually add no more than 10,000 Mw this year," said a power ministry official. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| On peak deficit, the official said: "It is a one-off case, it is an exception." | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
However, the power generation is up. Against 53,963 million units (MUs) generated in September, about 56,547 MUs were generated in October, an increase of 4.6 per cent.
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| The overall power supply position (non-peak power) also improved to 7.3 per cent. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Regionwise, western India, which has industrialised states like Maharashtra and Gujarat, continued to reel under peak power and energy shortage. While the peak shortage in the region was 26.6 per cent in October, the energy shortage was 15 per cent. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Maharashtra had a peak deficit of 26.8 per cent and energy shortage of 19 per cent. In the northern region, Uttar Pradesh was one of the worst performers with an energy shortage of 14 per cent and a peak deficit of over 18 per cent. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Conceding that capacity addition was unable to keep pace with demand, the official cited shortage of equipment and manpower as the main reason for the sector's non-performance. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| "An acute shortage of vendors for balance-of-plant equipment is also delaying the commissioning of plants," said a power ministry official. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Industry experts say capacity addition should be accompanied with power reforms, especially those aimed at reducing transmission and distribution losses and theft. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app