The NDA government has increased the targets for setting up solar capacity five times to 1,00,000 megawatt (Mw) by 2022.
| PLACE IN THE SUN |
|
The RPO for solar power set by the regulators for the states is in the range of 0.10-0.50 per cent of their total power procurement. The RPO provision has been increased to eight per cent for solar power in the revised national tariff policy. The states were now working out their plans and awarding projects, said Kapoor, adding the southern states were taking the lead.
Andhra Pradesh, for instance, will need 5,678 Mw of renewable energy capacity in 2022 under the revised RPO. The state has commissioned 573 Mw and tendered 4,096 Mw during 2015-16. The balance 1,009 MW will be tendered this year.
Karnataka will need 6,671 Mw in 2022. It has commissioned 45 Mw and tendered 4,464 Mw in 2015-16. The state is likely to tender 2,062 Mw this year.
As tariffs fall with every tender, the Centre is of the view that sub-Rs 5 per unit tariffs are feasible. "Bidders are coming with low tariffs on their own without any compulsion from the government, which implies these tariffs are workable. Bidders who have offered this tariff have issued bank guarantees and therefore will take up construction work," Kapoor said.
Debunking concerns of large-scale financing, ministry officials said the government was in constant touch with financial institutions to make available the required money. "Private developers are also making efforts to get equity and loan finance. While financing is challenging, it is not true that no fresh equity is flowing in. Had this been the case, 7,000 Mw of renewable capacity would not have been commissioned in 2015-16. Work is going on, and a large number of projects will be commissioned this year," Kapoor pointed out. As states float mega solar power projects, the Centre is trying to match them in evacuation of power. Ministry officials said a large number of sub-stations had spare capacity where new projects could immediately be connected. "For the long run, solar parks with connectivity are being developed. Also the green corridor projects have taken off and transmission lines are under construction in Tamil Nadu and Rajasthan," Kapoor said.
Business Standard had reported last month the second phase of the green corridor to connect 33 upcoming solar power parks was likely to be awarded through tariff-based competitive bidding during this year. The first phase is being built by state-owned Power Grid Corporation.
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app
)