MNRE issues bidding Guidelines for setting up 1000 MW Wind Power Projects connected to ISTS scheme

Image
Capital Market
Last Updated : Nov 03 2016 | 12:47 PM IST
Ministry of New and Renewable Energy (MNRE) issued Guidelines for transparent bidding process for implementation of Scheme for setting up of 1000 MW Wind Power Project connected to inter-state transmission system (ISTS).

As per Guidelines the Wind Power Projects will be selected through open and transparent competitive bidding followed by e-reverse auction and the capacity may go higher than 1000 MW, if there is demand from Buying Entities. The implementing agency SECI has already floated RfS document for selection of bidders under the Scheme.

Discoms of non-windy State and UTs and also the bulk consumers of any State/UTs who intend to buy 10 MW or more can buy wind power under the Scheme.

PTC India, trading company selected by SECI under the scheme, will sign Power Purchase Agreement (PPA) with wind projects at bidded tariff and back-to-back Power Sale Agreement (PSA) with Buying Entities at a pooled price of the total bids selected. The term of PPA and PSA will be 25 years.

Bidder can bid for a minimum capacity of 50 MW and maximum up to 250 MW. The selected bidder is required to injected wind power at ISTS interconnection point. Bidder is allowed to install 5% of additional rated capacity that will compensate auxiliary consumption and system losses up to interconnection point.

Provision relating to pass through of GST impact, part commissioning, efficiency in generation, performance monitoring have also been stipulated in the guidelines.

The Guidelines are available at http://mnre.gov.in/file-manager/grid-wind/Scheme-for-Setting-up-of-1000-MW-ISTS-connected-Wind-Power-Projects.pdf

BACKGROUND

Ministry sanctioned a Scheme for setting up of 1000 MW ISTS connected Wind Power Project on 14 June 2016.

The objective of the Scheme is to encourage competitiveness through scaling up of project sizes and introduction of efficient and transparent e-bidding and e-auctioning processes. It will also facilitate fulfilment of Non-Solar Renewable Purchase Obligation (RPO) requirement of non-windy states.

In order to facilitate transmission of wind power from these windy states to non-windy states provisions have been made in the Tariff Policy to waive the inter-state transmission charges and losses for wind power projects and Ministry of Power has already issued order in this regard.

Powered by Capital Market - Live News

Disclaimer: No Business Standard Journalist was involved in creation of this content

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Nov 03 2016 | 12:15 PM IST

Next Story