Haven't got possession of flat? Claim refund if project delayed beyond a yr

In case of non-delivery of projects within the prescribed deadline, the builder will refund the entire amount with 10% interest

real estate, housing projects, home refund, delayed possession of flats, delayed real estate projects in india, homebuyers, realty, NCDRC, builder bankruptcy, realty property, builder buyer dispute, house refund, delayed house completion, property
Representative Image
BS Web Team New Delhi
3 min read Last Updated : May 17 2019 | 1:11 PM IST
The National Consumer Disputes Redressal Commission (NCDRC) has come to the aid of homebuyers who struggle to get possession of their flats for years. The apex consumer commission has determined a time period of one year for stalled realty projects beyond which homebuyers can claim refund from builders.
 
NCDRC has mandated real estate builders to refund the homebuyers for failing to hand over the possession of an apartment in case of a delay.

According to a report in the Times of India, NCDRC said in an order that, "It is now established that allottees have the right to ask for a refund if possession is inordinately delayed, particularly beyond one year."


Despite the Supreme Court and several consumer courts repeatedly saying that homebuyers cannot be made to wait indefinately for their flats, there was no clarity as to when a buyer can claim a refund for the unfinished or delayed project.

The order was passed on a plea filed by a Gurgaon resident who bought one flat in 2012. He paid Rs 90 lakh against the total cost of Rs 1 crore and the flat was promised to be handed over to him within 36 months with a grace period of six months from the date of allotment. When the builder failed to give the possession of the apartment, the buyer approached the commission to seek a refund on the time-bound possession of the flat. 


NCDRC ordered the builder to complete the construction work, handover the apartment by September 30, 2019 in all aspects according to the agreement. The commission also asked the builder to pay interest at 6 per cent on the deposited amount. 

According to NCDRC, in case of non-delivery of projects within the prescribed deadline, the builder will refund the entire amount with 10 per cent interest.

In a recent example, NCDRC asked real estate giant Unitech Limited on May 14 to refund over Rs 1 crore to a home buyer for failing to hand over the possession of an apartment. The apex consumer commission asked the company to refund within three months Rs 1,77,95,300 and give a compensation of simple interest at 10 per cent per annum to Gurgaon residents Amal and Minakshi Ganguli for a delay of over two years in handing over the possession.

One subscription. Two world-class reads.

Already subscribed? Log in

Subscribe to read the full story →
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

Next Story