46,000 MW power projects facing viability issues: Crisil

Image
Press Trust of India New Delhi
Last Updated : Jul 28 2015 | 5:32 PM IST
Power projects with around 46,000 MW capacity are facing viability issues due to lack of long-term purchase agreements, inadequate fuel supply and aggressive bidding to win projects, says a Crisil report.
Out of this 46,000 MW, about 36,000 MW are coal-based projects within which tariff under-recovery has impacted 20,000 MW of capacities, while the rest are reeling because of inadequate feedstock and poor electricity offtake by discoms, the rating agency said in a release.
The remaining 10,000 MW of gas-based projects have become unviable because of dwindling fuel supplies from the Krishna-Godavari basin.
"Total loans to these stressed generation projects are currently about Rs 2.1 lakh crore. A sixth of it, or about Rs 35,000 crore, is for projects which have the cushion of a strong parent.
"Additionally, projects with loans of Rs 1 lakh crore could become viable if their payment profiles can be structured appropriately. This leaves the remaining Rs 75,000 crore of loans at risk," said Chief Analytical Officer, Crisil Ratings Pawan Agrawal in the statment.
Another Rs 1.9 lakh crore of debt is owed by weak discoms for which moratorium on principal repayment - based on a financial restructuring package (FRP) announced in 2012 -- ends in the current and next fiscal. Till date, the government support has prevented these discoms from turning weak, it added.
Assurance of continuing financial support is necessary, else this debt, too, can be at risk. After the FRP, states and discoms did not follow through fully with measures to improve financial discipline and commercial orientation. The FRP, thus, provided only a liquidity respite.
Discoms will continue to face liquidity pressure till there are appropriate tariff hikes and a significant reduction in aggregate technical and commercial (AT&C) losses from the current level of 25.4 per cent.
Crisil believes significant efforts to augment domestic coal production and improvement in the ability of discoms to sign long-term PPAs are critical going forward.
While the government has taken some positive steps to improve fuel availability through coal block auctions and gas subsidy, these provide only limited relief and the plant load factor of capacities commissioned after fiscal 2009 will remain sub-optimal at 45 per cent.
And, if discoms remain financially fragile and stay away from signing power purchase agreements (PPAs), capacities at risk will increase, it said.
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Jul 28 2015 | 5:32 PM IST

Next Story