Buyers cannot be made to wait indefinitely for possession of property, says NCDRC

Image
Press Trust of India New Delhi
Last Updated : May 22 2019 | 5:46 PM IST

Buyers cannot be made to wait indefinitely for possession of their properties, the apex consumer court has said and directed a Gurugram-based developer to pay over Rs 1.15 crore refund to a man for not delivering his flat on time.

The National Consumer Disputes Redressal Commission (NCDRC) said the housing developers' action of relying on the clause of force majeure, while retaining the amounts deposited by complainant, is not only an act of deficiency of service but also of unfair trade practice.

Force majeure is a contract provision which relieves parties from performing contractual obligations if unforeseeable circumstances beyond their control arise.

"We are of the view that the complainant cannot be made to wait indefinitely for the delivery of possession and the act of the opposite party (developer) in relying on Force Majeure clause while retaining the amounts deposited by the complainant, is not only an act of deficiency of service but also of unfair trade practice," the commission's bench comprising President R K Agrawal and member M Shreesha said.

The bench passed the order while allowing a complaint filed by Ashok Kumar Taneja who had booked an apartment with Orris Infrastructure Private Limited in Gurugram and paid over Rs 1.15 crore from May 2012 to December 2016.

According to the complainant, the developer had promised to hand over the possession of the apartment in December 2015.

He said more than seven years have lapsed from the date of agreement but he has not got the property.

The bench also held as "extremely unfair" and "onesided" the force majeure clause along with others such as the developer charging interest at 18 per cent for any delay in payments made by flat purchasers, but at the same time if the project is abandoned, refund would be made at an interest of nine per cent only.

The commission allowed Taneja's plea and directed the developer to refund the principal amount, that is, over Rs 1.15 crore with interest at 12 percent per annum.

It also directed the developer to pay litigation cost of Rs 25,000 to Taneja.

"The complainant cannot be made to wait indefinitely for possession of the unit, as the construction is yet to be completed even after a period of more than 7 years has lapsed from the date of agreement. Therefore, we are of the considered view that the complainant is entitled for refund of the principal amount with reasonable interest," said the Commission.

The counsel appearing for the developer submitted that the time given for completion of the project before the RERA was June 30, 2020 and it would be completed as on that date.

However, Taneja's counsel said that he was not willing to wait till June 30, 2020 for taking possession as promised date of delivery of possession was way back in December 2015.

Disclaimer: No Business Standard Journalist was involved in creation of this content

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: May 22 2019 | 5:46 PM IST

Next Story