The Comptroller and Auditor General (CAG) has pointed out that there were significant delay for nine parachute items for the armed forces by the ordnance factory in Kanpur and deficiencies of these items to the extent of 33 to 100 per cent.
The Ordnance Parachute Factory Kanpur (OPF) manufactures various parachutes for the armed forces. Users' requirement of parachutes is of significant importance because of their strategic use in man carrying, supply drop, emergency escape of pilots from aircraft, for aborted take-off and to reduce landing run length of aircraft.
The audit was conducted at the OPF and Ordnance Factory Board (OFB) for 2012-13 to 2016-17 on production of 11 selected parachutes for the Indian Army and Indian Air Force (IAF) to ascertain whether OFB supplied quality parachutes to the users in time and as per their requirements.
The audit found that there were deficiencies in production planning like delays in holding target fixation meetings, non-identification of item-wise production capacity and production constraints/capacity shortage not highlighted in the meetings for fixing realistic targets.
The targets were routinely revised downwards mid-year due to OPF's "inability" to meet the target because of non-availability of quality metal components/fabrics and scarcity of vendors, the report said.
"Out of 49 instances analysed, OPF achieved production target only in five instances during 2012-13 to 2016-17. The shortfall occurred mainly due to delayed procurement and receipt of input materials, limited vendor base and delay in resolving drawing/specification issues.
"As a result, there were significant outstanding orders for nine parachute items as of March/April, 2017. The users' also had deficiencies of seven parachute items to the extent of 33 to 100 per cent," the report observed.
Bulk production of two types of Heavy Drop (HD) parachutes, developed by the Defence Research and Development Organisation (DRDO) in 2000 and 2009 for the Army and Navy could not be commenced due to the delayed receipt of drawing specification, delayed supply of pilot lot by OPF for validation trial and production constraints at sister factory for HD platform system, the report said.
The Army's requirement of combat free-fall parachute, developed by the DRDO in 2006, was not fulfilled due to "life threatening defects" observed by the Army in validation trials and non-resolving the quality problems the by OPF and the DRDO, it observed.
Disclaimer: No Business Standard Journalist was involved in creation of this content
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app