BharatNet, called the National Optical Fibre Network, is aimed at providing 100 Mbps broadband connectivity to more than 2.50 lakh gram panchayats across the country.
The progress of the BharatNet project implementation has been slow due to a variety of reasons, including the "inability of Bharat Broadband Network Limited" to procure optical network termination equipment in time as well as "major gaps in the implementation strategy", Union Secretary for Information Technology and Communications J S Deepak said.
The first phase envisages providing one lakh gram panchayats with broadband connectivity by laying underground OFC lines by March 2017, Deepak said in a letter to Chief Secretaries of all states last week.
"The second phase will provide connectivity to all 2,50,500 gram panchayats in the country using an optimal mix of underground fibre, fibre over power lines, radio and satellite media. It is to be completed by December 2018," the Union Secretary said.
"For success in phase-2, which will also involve laying of OFC over electricity poles, the participation of states will be important. This is a new element of the BharatNet strategy as the mode of connectivity by aerial OFC has several advantages, including lower cost, speedier implementation, easy maintenance and utilisation of existing power line infrastructure," he pointed out.
In the third phase from 2018 to 2023, state-of-the-art, future-proof network, including fibre between districts and blocks, with ring topology to provide redundancy would be created, Deepak elaborated.
In laying aerial OFC, the states and power distribution companies have a critical role, which would include digital mapping of the locations of substations and electrical poles from Blocks down to GPs.
"The most remarkable feature of Andhra Pradesh mapping has been that the entire state-wide mapping was accomplished in a week. After the mapping, the state has laid about 10,000-km of aerial OFC on electrical poles in a time of three months," Deepak said.
"States are, hence, encouraged to follow the procedure adopted by Andhra Pradesh," the Union Secretary told the Chief Secretaries in the letter.
Digital mapping of power lines would be a useful tool that could be used for other applications, including installation of smart meters in rural areas in future, he said.
BharatNet, launched in 2013, is being implemented by the Department of Telecom. It is funded by the Universal Service Obligation Fund (USOF).
The project executing agency Bharat Broadband Network Limited is implementing it through three Central Public Sector Enterprises -- BSNL, Power Grid and RailTel.
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app