The agency today carried out search operations at four places including one in Mumbai and three places in Sambalpur, Odisha after registering the case, CBI sources said.
It is alleged that the coal was used by the company in an unauthorised manner in the existing power plant whereas the allocation was done for expanding the capacity of new power plant, the sources said.
The agency has also alleged that mining was started by the company wihout obtaining the mandatory permission.
Public servants, the agency alleged, facilitated the illegal operations by not taking action against unauthorised use despite their knowledge.
Talabira-I coal block in IB valley in Odisha, with nearly 22.55 million tonnes of geological reserves, was allotted to Indal on February 25, 1994.
"In continuation with their investigation into 185 coal mines across industry, the CBI has now begun its investigation into Talabira-I, a mine allocated in 1994 to the erstwhile Indal, which was later acquired by Hindalco. In this connection, the CBI carried out searches in three of the Company's sites," the Aditya Birla group spokesperson said.
The agency had filed a closure report in the allocation of Talabira-II which has been rejected by the Special Court which directed CBI to re-investigate the matter.