Apex consumer commission NCDRC has directed a real estate developer to refund over Rs 4 crore along with interest to its customer, saying complainants cannot be made to wait indefinitely for possession.
The National Consumer Disputes Redressal Commission (NCDRC) has directed a Haryana developer to pay Rs 4.12 crore to Alok Kumar, currently residing in Japan, noting that the construction is yet to be completed after a lapse of more than six years from the date of booking.
"The complainants cannot be made to wait indefinitely for possession of the unit, as the construction is yet to be completed even after a period of more than 6 years has lapsed from the date of booking," NCDRC President R K Agrawal and member M Shreesha said.
The commission awarded Kumar interest on the principal amount after noting that he had taken loan from a bank for buying the apartment and had undergone "mental agony" and "monetary loss as Golden Peacock Residency Private Limited, the developers, failed to deliver possession of the flat.
"The interest is being awarded as it is seen that the complainant has paid interest to HDFC Bank Limited and has also undergone mental agony and monetary loss as the developer not only could not complete the construction on time and deliver possession of the said flat but also could not give any further promise with respect to the future delivery of possession of the subject flat," the commission said.
It also directed the developer to pay Rs 25,000 to Kumar towards litigation cost.
According to Kumar's complaint, he was looking for a residential accommodation upon his return to India from Tokyo and had booked an apartment with Golden Peacock Residency in its project, 'Micheal Schumacher World Tower', in Gurgaon, Haryana.
By September, 2015, Kumar had paid Rs 4.12 crore in total.
Kumar alleged in his complaint that during his visit to India in 2015, he was "shocked" to see that the construction work had been completely stopped since 2015.
He was informed that there was some dispute with the construction company due to which the work had stopped. However, he was assured that the project would soon be completed.
Despite repeated assurances, the construction was never resumed and in April, 2018, Kumar found that the site office of the developers was locked, after which he sent them a legal notice.
Disclaimer: No Business Standard Journalist was involved in creation of this content
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app