Delhi govt's project to procure 1,000 e-buses delayed by one year

Image
Press Trust of India New Delhi
Last Updated : Jun 07 2019 | 8:55 PM IST

The Delhi government's ambitious project of procuring 1,000 e-buses to combat alarming air pollution in the national capital has been delayed by at least one year, showed the outcome budget 2019-20 released by Deputy Chief Minister Manish Sisodia on Friday.

The process of procuring the electric buses by the Delhi government was delayed for various reasons, including the model code of conduct which was in place for the Lok Sabha polls, showed the document.

The government had approved calling tenders for the first batch of 385 full-electric buses on March 2 this year. The tenders were floated on March 10 but the process was interrupted due to the poll conduct, said the outcome budget of the transport department.

"As per the revised schedule, the bids will be received on July 10, 2019. Induction schedule of the buses will be delayed accordingly," it said.

The bids will open on July 30, 2019, and supply of buses by the manufacturer to the concessionaire will begin in March 2020. The roll out was originally scheduled to begin from March 31, 2019, timeline for the project showed.

Also, induction of 1,000 low-floor buses through the Delhi Transport Corporation (DTC) will also be delayed as an earlier tender floated by the public transporter was scrapped since only one bidder had turned up.

The Delhi Cabinet will extend approval for fresh bid on June 20.

The first lot 38 such buses is scheduled to arrive 25 weeks after the date of Cabinet decision. The rest will arrive in batches of 240 and the entire fleet will arrive by 41 weeks of the Cabinet decision, showed outcome budget document.

The roll out of 1,000 standard-floor buses fitted with lifts for specially abled people will begin from July and the entire induction process will conclude by November, it said.

The outcome budget showed that the engagement of 1,000 low-floor buses by the transport department under the cluster scheme will begin in November with at least 25 per cent buses fetched in first lot. The induction process will be completed by February 2020.

Disclaimer: No Business Standard Journalist was involved in creation of this content

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Jun 07 2019 | 8:55 PM IST

Next Story