A bench of Chief Justice J S Khehar and Justices N V Ramana and D Y Chandrachud allowed the plea of CAG seeking time to submit a report after verifying the claim of the company and listed the matter for final hearing after eight weeks.
The apex court had on November 11, 2016 asked CAG to assist in the matter and verify the company's claim that the total cost of the project has not been recovered and submit a report within four weeks.
The court had passed the order while disagreeing with the company that its refusal to stay the Allahabad High Court's verdict making DND flyway toll free for commuters would cause irreparable loss to the firm.
It had said that while the company can be compensated later if it succeeds in its appeal, it will be impossible to provide restitution to the lakhs of commuters from whom the toll fee would be collected to repay them on dismissal of the special leave petition (SLP).
The high court had brought cheers to millions of commuters by ruling that no toll will be collected henceforth from those using the 9.2 km-long, eight-lane DND flyway. The order was passed when the high court allowed a PIL by the Federation of Noida Residents' Welfare Association.
The firm had challenged the high court verdict saying it
To this, the apex court had said prima facie the issue that arose in the appeal required a detailed scrutiny as conflicting claims have been made regarding recovery of the total cost of the project by the concessionaire.
"To resolve the dispute, it is appropriate that an independent agency is requested to examine the relevant records of the DND flyway. The said agency should examine the reports of the independent auditors appointed by the petitioner and submit a report regarding the correctness of the petitioner's claim that the total cost of the project has not been recovered," it had said while asking CAG to verify the firm's claims.
The court had said that the "right to levy and collect user fee from the commuters as conferred upon the concessionaire under the concession agreement suffers from excessive delegation and is contrary to the provisions UP Industrial Development Act".
It had noted that "the concessionaire, according to their own financial statements, has recovered Rs 810.18 crore (approx) from toll income from the date of commencement of the project till March 31, 2014 and after deduction of operation and maintenance expenses and corporate income tax, the surplus was Rs 578.80 crore (computed before interest, depreciation, and lease rental received by the concessionaire)".
"We are, therefore, more than satisfied that the concessionaire cannot now recover the user fees from the users/ commuters of the Noida Toll Bridge the DND Flyover," the high court had said.
