With this, the total penalty on RIL for missing the target in four fiscal years beginning April 1, 2010 now stands at a cumulative USD 2.376 billion, the Minister informed the Lok Sabha today.
The penalty is in the form of disallowing costs incurred. The Production Sharing Contract (PSC) allows RIL and its partners BP Plc and Niko Resources to deduct all capital and operating expenses from the sale of gas before sharing profit with the government.
In a written reply to a question, Pradhan said gas output from the Dhirubhai-1 and 3 gas field in the eastern offshore KG-D6 block was supposed to be 80 million standard cubic meters per day but actual production was only 35.33 mmscmd in 2011-12, 20.88 mmscmd in 2012-13 and 9.77 mmscmd in 2013-14.
This year the output has been only 8.05 mmscmd.
His ministry on July 10 issued a notice disallowing USD 579 million in cost for output lagging targets in 2013-14.
Pradhan said the issue is currently under arbitration.
"The Ministry of Petroleum and Natural Gas has also raised a claim of additional profit petroleum to the tune of USD 115 million to be paid by the contractor, on account of disallowance of cumulative contract costs of USD 1.797 billion, till 2012-13," he said.
After including cost disallowance in 2013-14, the total additional profit petroleum claimed from RIL comes to USD 195 million, he said.
The Minister said RIL had put up production facilities to produce 80 mmscmd of gas but "has failed to adhere to the approved field development plan in terms of drilling and putting on stream the required number of wells."