According to officials, the leakage of heavy water that is used in cooling off the nuclear reactor core was detected around 9 am and it was fixed in some time and the temporary emergency was lifted shortly afterwards.
Surat District Collector Rajendra Kumar said there was no leakage of radiation at the plant and the situation was under control.
KAPS site director L K Jain in a statement said radiation levels in and outside the plant are normal.
"Unit-1 of KAPS, which was operating at its rated power, was shut down at about 9:00 Hrs today. Consequent to a small leak in Primary Heat Transport (PHT) system, the reactor was shut down as intended as per the design provisions. All safety systems are working as intended," the statement said.
"The radioactivity/radiation levels in the plant premises and outside are normal. KAPS 1 and 2 consists of two Units of Pressurized Heavy Water Reactors of 220 MWe each," Jain added.
"The director of the plant informed me that unit-1 has been shut down following a problem in the primary heat transmission system. There was some leakage of heavy water that is used in cooling the reactor core. At present, the situation is under control," Rajendra Kumar told PTI.
According to KAPS website, the power station has two generation units of Pressurised Heavy Water Reactors (PHWR) that were commissioned during early 90s.
"The problem was detected in the morning and it has been fixed as of now. The plant also declared temporary emergency, which has been lifted after some time. As of now, there is no emergency and things are under control. We are told that Unit-1 will take some time to start functioning again," Kumar added.
Tapi District Collector B C Patni also confirmed that there was no report of radiation leakage.
(Reopens DEL49)
Meanwhile, the Atomic Energy Regulatory Board (AERB) said that a team of additional experts is being deputed for independent assessment of the situation at the affected plant.
"An expert from AERB is already at the KAPS site and a team of additional experts are being deputed for independent assessment of the situation at the plant. We have also asked (NPCIL) to keep the unit shut till the incident is fully investigated and corrective actions are taken," the AERB said in a statement.
However, the regulatory body clarified that all the safety functions of the reactor are currently functioning satisfactorily and there has not been any abnormal release of radioactivity outside the plant or radiation exposures as a result of the incident.
The second unit of the project has been shut down since July last year and AERB is monitoring its status closely, it said.
