The building fell like a pack of cards and thick, huge columns of smoke engulfed the area with birds scurrying to safety.
Columns in the 11-storeyed structure were filled with explosive substances and brought down using implosion technique, employing controlled blasting of explosives.
Timer devices were used and the multiple blast was carried out sequentially by using a remote. Columns were drilled and explosive substance was stuffed.
Anxiety prevailed as the demolition was delayed by over two hours.
Before the demolition was carried out, the structure was weakened by removing some portions like walls.
A posse of police cordoned off the area and residents living about 100 meters near the building were requested to keep off and fire tenders and ambulances stationed in the vicinity.
The residents were housed in a nearby hall till the completion of the building's demolition. Traffic diversions were made and power supply in the vicinity was switched off during the time of demolition as part of safety measures.
Police Commissioner S George inspected the spot ahead of demolition and reviewed security measures. Kancheepuram District Collector R Gajalakshmi and senior officials, including those from Revenue and Chennai Metropolitan Development Authority, were present.
On June 28, 2014 one of the two blocks of an under construction residential building at suburban Moulivakkam had collapsed, killing 61 workers and injuring scores of people. That collapsed structure was also 11-storeyed.
Subsequently, the adjacent block too was declared unsafe by the authorities. An order for demolition of the unsafe structure had been issued under 141 Cr P C.
Kancheepuram District Collector Gajalakshmi said the
structure was brought down in five seconds.
On the delay in carrying out the demolition, she told reporters it was drizzling and that the contractor wanted some time to carry out tests.
"He took some time for that. The delay was due to rain," she said.
Against the background of claims that rules do not allow such demolitions after sunset, she said that with proper lighting and safety measures, there is a provision that allows carrying out the implosion after sunset. "We have done this properly according to rules."
Contractor P Ponlingam, CEO of Maglink Infra Projects Limited, said all types of permitted explosives were used to carry out the implosion.
"The strength of columns, reinforcements and size were all taken into consideration to determine the requirement of explosives and after doing lab tests we have done this. The building fell down exactly in the direction it was supposed to fall and it happened as per plan," he said, adding that the cost involved was about Rs 50 lakh.
