A bench of Chief Justice Dipak Misra and Justices A M Khanwilkar and D Y Chandrachud stayed the November 19, 2016, order and issued notice to petitioners who were before the high court.
Uttarakhand government had filed the appeal through advocate Farukh Rasheed saying the high court had erred in passing several mandatory directions which were not harmonious with the guidelines of National Disaster Management Authority (NDRF) and SDRF, for rehabilitation of the affected people.
Rasheed said that out of 258 damaged bridges, 136 have been repaired and made available for traffic.
"At 21 locations, reconstruction of bridge is not required because of availability of alternative connectivity. As such, only 101 washed out bridges are to be reconstructed against which 25 bridges have so far been reconstructed and 10 are under constructions," he said.
The state government said the Asian Development Bank and World Bank have approved funding for "Uttarakhand Disaster Relief Project (Road and Bridges)" under which reconstruction and strengthening of 866 roads of 3567 km length costing Rs 970.30 crore is to be done in a span of four years.
Several roads, buildings and other structures were washed away and, according to the state government's plea, the estimated death toll was around 10,000, with over 3,000 persons missing.
The high court had in its order directed the state government to complete the construction of 10 bridges, within one year and completion of tender process for 16 bridges within a period of two months.
It had said the remaining damaged 49 bridges would also be reconstructed within one year along with four washed out roads within two years.