Kochi Metro work hit by quarry owners' strike, says DMRC

Image
Press Trust of India Kochi
Last Updated : Sep 24 2015 | 6:42 PM IST
The ongoing strike by quarry owners in Kerala has affected the pace of work on Kochi Metro and it may even miss its target date of June 2016 for start of commercial operations, Delhi Metro Rail Corporation (DMRC) said today.
Expressing concern over the strike launched on September 14, DMRC, which is implementing the Rs 5,181.79 crore project, said the existing stock of aggregates would last only for a couple of days and if the supplies did not resume, the work would come to a grinding halt.
A DMRC release said the strike has adversely affected the work of project.
"As of now, out of 6,000 workers involved in the project, 4,000 workers are idling due to non-availability of materials at site and balance 2,000 workers will also become idle on account of no work at site," it said.
In the past it had instructed contractors to keep sufficient stock of aggregates anticipating frequent strikes, but despite this, the prolonged quarry strike had affected the pace of work and stock available was getting exhausted.
DMRC fears that since the workers are idling at site, there is every possibility of them advancing their plan to go to their native places --north India -- for the ensuing Pooja festival.
Once the labourers return to their native places, they may come back only after two months and thereby the precious time of the project will be lost, the DMRC said.
The construction of station building and other allied works, which are in a critical and advanced stage, require more labour strength, it said.
"In case quarry strike continues, it is apprehended that the project will miss the target date of June, 2016," the release said.
The quarry owners under the banner of All Kerala Crusher and Quarry Owners Association are on the indefinite strike demanding a revision in mining rules formulated recently.
Announcing the government's decision to exempt from environment clearance quarries functioning in one hectare land, Chief Minister Oommen Chandy had on September 16 said there was shortage of materials even for development projects.
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Sep 24 2015 | 6:42 PM IST

Next Story