MADC could not develop any airport in Maha in 14 years: CAG

Image
Press Trust of India Mumbai
Last Updated : Apr 07 2017 | 7:22 PM IST
Despite 14 years of its existence, Maharashtra Airport Development Company (MADC) has not developed a single airport in the state due to absence of a long-term plan, the Comptroller and Auditor General has said.
The CAG report, tabled in the Maharashtra legislature today, said that decisions were being taken on ad-hoc basis without any firm development model and long-term plan.
There were avoidable delays in acquiring the land, while in some cases excess land was acquired which lay unused, it noted.
MADC was set up in August 2002 to plan, construct, operate and maintain airports. The government entrusted the company the task of developing three 'greenfield' and six 'brownfield' airports, and a heliport at Gadchiroli.
The greenfield airports were to come up at Pune, Shirdi, Solapur, while brownfield airports were to be developed at Amravati, Chandrapur, Dhule, Karad, Nagpur and Phaltan.
However, CAG pointed out, development of airports was hit by hurdles.
The site for airport at Pune has not been finalised due to restrictions imposed by the Indian Air Force (which has an air base there), natural obstructions and opposition from land owners.
The pre-feasibility study expressed concerns regarding commercial viability of Karad airport in western Maharashtra, as the location is close (70 km) to the existing airport at Kolhapur.
Dhule airport was also found to be not viable, while feasibility study of Chandrapur airport in Vidarbha indicated that the extension of runway of the existing airport was not possible.
It was decided that a new airport should be developed in Chandrapur, but the site was yet to be finalised.
As to the airport at Phaltan, MADC had not made any plans yet, the CAG said.
Grants given by the state government for development of airports were lying unused, thus "blocking up" the public money, it said.
MADC should evolve a long-term plan for timely development and expansion of these projects and assess land requirement in advance so as to avoid delays and "idling" of funds, the CAG said.

Disclaimer: No Business Standard Journalist was involved in creation of this content

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Apr 07 2017 | 7:22 PM IST

Next Story