There were also delays in implementation of projects and inability of the agencies to either file patents or publish research papers as envisaged in the projects, the government auditor said.
According to the CAG report tabled in Parliament today, the ministry sanctioned 190 projects at a cost of Rs 545.90 crore during 2007-14 to various R&D organisations, of which 112 were completed and 78 were under progress.
Report 34 of 2015 on Ministry of New and Renewable Energy, CAG said: "Realisation of deliverable outcome was not achieved in a majority of projects. This was partly due to the fact that industry participation could not be secured in the projects where it was envisaged, which limited the commercial exploitation of technologies developed."
As per the National Action Plan on Climate Change target of 8 per cent and 9 per cent purchase of electricity from renewable source for years 2012-13 and 2013-14, the national achievement was only 4.28 per cent and 4.51 per cent respectively, the CAG observed.
It was found that between 2010 and 2014, only 4.77 per cent of Renewable Purchase Obligation compliance was through renewable energy certificate (REC) mode whereas 95.23 per cent was through direct purchase of electricity from renewable energy sources.
Under the demonstration programme, Solar Photovoltaic power project developers availing Generation Based Incentive (GBI) were not eligible to avail Accelerated Depreciation (AD) benefit under the Income Tax Act.
CAG observed that this was not ensured by the Ministry/ Indian Renewable Energy Development Agency (IREDA) before releasing GBI claims of Rs 22.49 crore to Reliance Industries Ltd. This resulted in both GBI and AD being claimed by RIL in the period August 2010 to December 2012.
State Electricity Regulatory Commissions for the adoption of RPO targets in alignment with National Action Plan on Climate Change targets.
It also said that the ministry should introduce a comprehensive framework for creating awareness of CDM.
CAG said the ministry had had not formulated guidelines for net metering to provide an enabling environment for solar technology penetration at a decentralized level.
It found that against the target of 500 MW of Solar Thermal projects, 447.50 MW (90 per cent) had not been commissioned (February 2015).
Government land of 3,404 acres in Rajasthan leased to six Solar Thermal project developers had not been put to intended use so far, CAG found.
As many as 32 stations identified as potential sites allotted to private developers for setting up wind farms were not developed within the extended time frame.
In Tamil Nadu, the quantum of wind power backed down was 6,018.43 MUs during 2007-2014, the maximum backing down being in 2012-13 (1,155.27 MU) and 2013-14 (3,419.85 MU), resulting in a loss of revenue to the extent of Rs 2,040.25 crore during this period.
On Small Hydro projects it said that approved projects could not be completed due to negligence of contractors, midway changes in design, etc. Resulting in significant time and cost overruns.
CAG said the ministry must ensure that pre-requisites such as land and statutory clearances are obtained before the release of Central Financial Assistance to developers in order to avoid time and cost overruns.
It observed instances of non traceable biomass plants and inoperative plants as also those working at lower capacities, installed with different specifications than approved and using non-permitted fuels.
None of the developers had furnished the generation data to the ministry after the commencement of commercial generation of electricity.
It added that physical verification of sampled systems by Audit revealed that 26 per cent of the biogas plants were not working.
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app