Nevertheless, it imposed a fine of Rs five crores fine on AOL as environmental compensation after coming down heavily on the foundation for not disclosing its full plans and also on the DDA and Environment Ministry for their role.
Late in the night, the AOL announced that it will appeal against the NGT order. Any challenge to the NGT order usually lies with the Supreme Court.
As activists raked up the question of serious environmental violations on account of the event in which about 35 lakh people are expected to participate, President Pranab Mukherjee has already pulled out of the valedictory function on Sunday in which he was to speak.
There was still speculation whether Prime Minister Narendra Modi will open it on Friday. He is yet to take a decision whether to attend the inaugural function, official sources said.
But government rejected criticism saying Sri Sri Ravi Shankar was committed to environment protection and the issue cannot be discussed in the House when it is being considered by a tribunal.
"For the reason of delay and laches on the part of the applicant in approaching the Tribunal and for the reason of fait accompli capable of restoration and restitution, we are unable to grant prayer of prohibitory order and a mandatory direction for removal of construction and restoration of the area in question to the applicant at this stage," a bench headed by NGT Chairperson Swatanter Kumar said.
The tribunal said that as per documents placed on record it is evident that flood plains have been drastically tampered with and ramps, roads, compaction of earth, pontoon bridges and other semi-permanent or temporary structures were constructed without the requisite permission of the concerned authorities including Ministry of Water Resources.
"For the damage caused to the environment, ecology, biodiversity and aquatic life of the river, the Foundation should be held liable for its restoration in all respects. In that regard and in exercise of our powers under Sections 15 and 17 of the NGT Act, 2010, we impose an Environmental Compensation, initially of Rs 5 crores," the green panel said.