A bench headed by NGT Chairperson Justice Swatanter Kumar also declared that an environment compensation of Rs 50,000 will be imposed on anyone who dumps waste in the river.
The apex environment watchdog directed all authorities concerned to complete various projects including setting up of a sewage treatment plant and cleaning drains within two years.
It also said the Uttar Pradesh government should be "duty-bound" to shift tanneries within six weeks, from Jajmau in Kanpur to leather parks in Unnao or any other place it considers appropriate.
The tribunal also appointed a supervisory committee, headed by the secretary of the Water Resources Ministry and comprising IIT professors and officials from UP government to oversee implementation of the directions passed in its 543- page verdict.
It also asked the committee to submit reports at regular intervals.
The NGT said the concept of zero liquid discharge and online monitoring of affluents should not be applied to industrial units.
It said that all industrial units falling in the catchment area of river Ganga should be stopped from indiscriminate extraction of groundwater.
The green panel has divided the work of cleaning the river in different segments - Gomukh to Haridwar (Phase-I), Haridwar to Unnao (termed as segment B of Phase-I), Unnao to border of Uttar Pradesh, border of Uttar Pradesh to border of Jharkhand and border of Jharkhand to Bay of Bengal.
It has already delivered the verdict in December 2015 with regard to first phase between Gomukh to Haridwar.
The verdict came on a 1985 PIL of noted environment activist M C Mehta which was transferred to the NGT from the Supreme Court in 2014.
Disclaimer: No Business Standard Journalist was involved in creation of this content
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app
