"The plant erection will be completed by December 2016. It is not an easy task. It is challenging. People will have to work hard. Trial of machines or trial of the plant will start by December 2016. Production will start in the middle of 2017," the PSU's CMD Narendra Kothari, who superannuated today, told PTI.
NMDC is in the process of setting up a steel plant in Nagarnar in Chhattisgarh with an investment outlay of over Rs 15,000 crore.
The iron ore will be supplied to the plant at market price, not on transfer basis, a senior company official said.
"The capacity of the steel plant will be about 60 per cent for the first year and would go up gradually to 100 per cent over a period of time," the official said.
On the iron ore market situation, Kothari said the sluggishness in ore prices may remain for the next two years internationally. However, there can be some uptrend in the domestic market if some initiatives, such as anti-dumping duty on steel products, are put in place.