Under a new policy, the national transporter has virtually forbidden the issuance of tenders or start of work on any new project without land in hand or a written assurance from the state government guaranteeing land to the railways within a specific time frame.
"The (Railway) Board has decided that issue of tenders or commencement of physical work for new line projects shall be taken up only after completion of land acquisition," the new policy says.
Currently, only 70 per cent of the land needed to be acquired to start a project, which often led to stoppages and delays because of non-availably of land or earmarked land being caught in litigation.
Officials said that the existing policy did not define that the acquired line needed to be linear, so problems arose when projects would start having issues when part work begins and the next section of land was not available.
"This new policy also puts the onus on state governments to ensure that land is made available to the Railways if they want a new railway line. We end up losing on investments if land is not available," said an official.
An official gave the examples of the new line between Tindivanam and Nagari in Andhra Pradesh (179.2 km) sanctioned in 2006, and the 36-km-long route from Morappur to Dharmapuri, sanctioned at a cost of Rs 134 crore which have seen very poor progress primarily because of non-availability of land.
Officials said that there is cost escalation of around 10-15 per cent, every year due to such delays.
However, the policy makes certain concessions for the general managers and given them some discretionary powers. The policy says that the GMs may invite tenders if they are reasonably certain of the possibility of land acquisition in a reasonable time frame.
"A written assurance from the state government in this regard can be considered by the GM.
"Large projects can be divided into phases by GMs, however, after ensuring that each phase on completion yields commercial returns for railways," the policy stated.
This means that the GMs have the discretion of starting a project if a stretch of land is available in a commercially viable section of the entire project so that railway does not lose out on revenue.
The policy also said that project, where local support or state support is not forthcoming resulting in poor or no progress as well as old projects that have not made any headway to projects that are unlikely to give any tangible benefits to the railways, would need to be continuously reviewed.
The board has said that this new policy shall be followed in case of new projects or old projects where tenders have not yet been finalised.
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app
)