Solar projects likely to miss deadlines over Coronavirus outbreak: Crisil

According to the ratings agency, non-adherence to completion of timelines attracts penalties, including downward renegotiation of tariffs, as per the standards of PPAs

solar, energy, clean energy, green, renewable, power, project, pollution, environment, conservation, emission
Press Trust of India Mumbai
2 min read Last Updated : Feb 17 2020 | 10:46 PM IST

As many as 3 GW of solar projects worth Rs 16,000 crore could be at risk of penalties for missing their respective scheduled commercial operation date (SCOD) if the impact of novel coronavirus on trade with China prolongs, says Crisil.

According to the ratings agency, non-adherence to completion of timelines attracts penalties, including downward renegotiation of tariffs, as per the standards of PPAs.

India imports nearly 80 per cent of its solar modules from China, where trade has been impacted due to measures implemented to combat the spread of the virus.

The clampdown has forced several manufacturers to run their plants at low utilisation, or to stall operations altogether.

Besides, modules already manufactured are facing delays in transit to project sites on account of precautionary restrictions on transit at ports, it said.

"This puts at risk around 3 GW of solar projects worth Rs 16,000 crore, auctioned between July and August, 2018, which need to meet their SCODs by July 2020," Crisil's Senior Director Manish Gupta said.

He further said given the orders for modules are typically placed with a lead time of six months from SCOD, these projects are now in the process of either placing orders or receiving delivery of modules and any delay at this stage can prove costly.

Crisil, however, noted that to meet the commissioning timelines, the developers may choose to implement projects with more expensive modules sourced from locations other than China.

"But this could erode returns as the modules may be 15-20 per cent costlier, shaving as much as three percentage points off their returns. Also, developers can invoke the 'force majeure' clause in the PPA under which they can seek relief under unforeseen and uncontrollable events. However, this is yet to be tested and may face legal and regulatory hurdles," Gupta added.

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

Topics :solar projectssolar energyCrisil ratings

First Published: Feb 17 2020 | 4:02 PM IST

Next Story