"All the questions have been answered in the negative," a five-judge bench headed by Justice A R Dave said, while pronouncing its decision on the presidential reference received by it.
The judgement makes it clear that the Punjab Termination of Agreements Act, 2004 is "unconstitutional" and Punjab could not have taken a "unilateral" decision to terminate the water sharing agreement with Haryana, Himachal Pradesh, Rajasthan, Jammu and Kashmir, Delhi and Chandigarh.
Today's judgement implies that the 2004 Act was not in consonance with the apex court judgement of 2003 which had mandated the construction of the SYL canal that has been stalled.
By the 2004 Act brought by the then Congress government led by Amarinder Singh, the state had sought to nullify the SC verdict by stopping the construction of the remaining part of the SYL canal.
As per the agreement of 1955, signed between the states of Punjab, Pepsu, Jammu and Kashmir and Rajasthan, Punjab (including Pepsu) was allocated 7.20 Million Acre Feet (MAF) surplus waters of the Ravi and Beas estimated at 15.85 MAF, based on flow series of 1921-45, excluding pro-partition use, Rajasthan was allocated 8.0 MAF and Jammu and Kashmir 0.65 MAF.
This Section also provided that if no such agreement was entered into within two years of the appointed day, the Centre may by orders determine the shares of the States having regard to the purpose of the projects.
MAF, Punjab 3.5 MAF and Delhi 0.2 MAF out of the total water of 7.2 MAF to be allocated amongst the three from the total available 15.2 MAF water of the Satluj, Ravi and Beas. The remaining water was to go to other states, including Jammu and Kashmir.
The first litigation in the water sharing dispute came in 1976 when Punjab was dissatisfied and filed a suit in the Supreme Court challenging the validity of the Section 78 of the Reorganization Act. Haryana also filed a suit for implementing the Centre's notification of April 24, 1976
This channel was designed to be 121 kms in length in Punjab portion with a designed capacity of 6500 cs and 91 kms. in length in Haryana portion with a designed capacity of 7435 cs.
The portion of the canal in Haryana was started during October 1976 and was completed in June 1980 at an expenditure of Rs 56 Crore. In addition Haryana also spent about Rs 250 Crore for constructing the canal infrastructure in its area to utilize these waters. The new canal system so constructed included Sewani, Jui, Loharu, and Jawahar Lal Nehru (JLN) Lift Canals etc.
When Punjab failed to take up the construction of SYL Canal in their territory, Haryana filed a suit for implementation of the decision of the Centre on April 13, 1979 in the Supreme Court. Punjab also filed a suit in the apex court on July 11, 1979 challenging the orders of Centre of March, 1976.
Punjab Chief Minister Amarinder Singh has got this very agreement of 1981 and all other subsequent agreements annulled "to protect the interests of the border state" even though this agreement was signed with Indira Gandhi as Prime Minister.
Not only that the Prime Minister belonged to the Congress the three Chief Ministers of Punjab Darbara Singh, Haryana's Bhajan Lal and Rajasthan's Shiv Charan Mathur also belonged to the party.
Earlier in 1960 the Indus Waters Treaty was signed
between India and Pakistan under which water of the Ravi, Beas and Satluj were reserved for exclusive use by India after transition period.
Six years later in 1966 when Punjab was reorganized, the Section 78 of the Reorganization Act provided for the apportioning of rights and liabilities of the existing state of Punjab among the successor states (Haryana and Himachal Pradesh) in relation to the Bhakhra-Nangal project and the Beas project, by agreement entered into by the states after consultation with the Centre.
Paragraph 9 of this accord, bearing the question of sharing of river waters provided that the farmers of Punjab, Haryana and Rajasthan will continue to get waters not less than what they were using from the Ravi Beas system as on July 1, 1985. Water used for consumptive purposes will remain unaffected.
The construction of the SYL Canal was to continue and the canal was to be completed by August 15, 1986.
In pursuance of the Rajiv Longowal Accord the Centre- constituted a Tribunal namely Ravi Beas Waters Tribunal (Eradi Tribunal) on April 2, 1986.
The Punjab share was inclusive of 0.352 MAF of permissive use allowed by Rajasthan under clause (ii) of the 1981 agreement and subject thereto but was exclusive of the pre-partition use of 1.98 MAF as well as 0.32 MAF in Shah Nehar Canal areas.
The share of Haryana was 1.620 MAF and Rajasthan 4.985 MAF (This figure is exclusive of the pre-partition use of 1.11 MAF).
The Tribunal stressed the need for the completion of the SYL canal "at an early date since this canal is lifeline for the farmers of Haryana."
The Eradi Tribunal in its report increased the surplus Ravi Beas waters by another 1.11 MAF available downstream of run stations, fixed the total availability at 18.28 MAF. It provided Punjab 5.00 MAF, Haryana 3.83 MAF, Rajasthan 8.60 MAF, J-K 0.65 MAF and Delhi 0.20 MAF.
the three states, to allocate the remaining 4.831 MAF of un-allocated Ravi Beas waters below the run stations to the state of Haryana, while Punjab sought modification of Tribunal's findings regarding verification of waters used by the various states because it is contrary to the provisions of the "Punjab Settlement".
Punjab also challenged the decision of Tribunal that Haryana and Rajasthan are Indus Basin States being erroneous and also the Decision of the tribunal rejecting the contention of Punjab having sole proprietary/Ownership rights of Ravi-Beas rivers being against the legal provisions.
But due to disturbed conditions in Punjab, the tribunal could not assemble for conclusive hearing on these applications. The Tribunal was then adjourned sine die in April, 1989.
Realizing that the progress of construction of SYL Canal in Punjab portion was not going up to the targeted schedule, Haryana took up the matter with Prime Minister and at a meeting on December 16, 1986, it was decided that entire cost of SYL Canal will be borne by the Centre.
Haryana on November 23, 1990 wrote to Prime Minister to entrust the balance work to some Central Agency like National Hydel Power Corporation, Border Roads Organization (BRO) or any other suitable agency.
As a result, the construction of the canal was decided to be handed over to BRO by Government of India on February 20, 1991 but there could not be any progress.
Not only that there is uncertainty but a substantial amount of money spent has not been put to any use. The project cost which is being funded by the Centre since December 16, 1986 has escalated from Rs 176 Crore in 1983 to an estimated cost of Rs 601 Crore (11/94 price index level). The cost is likely to escalate further as an amount of Rs 679.90 Crore has been spent in Punjab portion up to September 2001.
SYL Canal is being misused by Punjab for passing their flood waters to Haryana territories, adding miseries to the farmers of Haryana, state irrigation department officials say.
After all the efforts of Haryana to persuade Punjab directly and through the Union Government to get the SYL Canal completed did not materialize, Haryana approached the Apex Court through suit No-1 of 1995 filed in November 95.
The Supreme Court passed an order on January 15, 2002 and directed Punjab government that SYL Canal should be completed within a period of one year. In case state of Punjab fails to accomplish the task within the stipulated period, then the Union Government should get the work done through its own agencies as expeditiously as possible.
Punjab enacted the Punjab Termination of Agreements Act, 2004 just two days before the July 15,2004 deadline when the Centre was to take over physical possession of the Canal from Punjab Irrigation Department and hand over the construction to the CPWD for completion of the disputed Canal.
Interestingly, none of the states that have been a party to the unsolved issue is a riparian state, except Punjab and Jammu and Kashmir. The other non-riparian states are Haryana, Rajasthan and Delhi.
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app
