Widening of Mithi river: NGT slaps Rs 25 lakh on MMRDA

Image
Press Trust of India New Delhi
Last Updated : Jun 03 2016 | 5:50 PM IST
The National Green Tribunal has imposed a cost of Rs 25 lakh on Mumbai Metropolitan Region and Development Authority (MMRDA) for not following due procedure to obtain coastal regulation zone (CRZ) clearance and causing environmental degradation while widening of Mithi river.

The green panel said MMRDA carried on with the widening of the river, construction and other allied activities on their project "without sanction of law" and was liable to pay environmental compensation.

"The project proponent MMRDA has started the project without compliance to the relevant provisions of law. It caused environmental degradation and even the blasting work was carried in violation to the relevant laws in force.

"Consequently, the respondent is liable to pay environmental compensation. At this initial stage, it is directed that the project proponent shall pay Rs 25 lakh as environmental compensation...," NGT Chairperson Justice Swatanter Kumar said.

The panel also asked State Level Environment Impact Assessment Authority (SEIAA) to consider the project as it exists today and mention the amount which should be imposed upon the project proponent for "its defaults, violation of laws and for causing damage to the environment, ecology and biodiversity of river Mithi".

"SEIAA shall also compute environmental, ecological and other damage caused by the project and the remedial steps required to be taken in that direction.

"SEIAA shall ensure that the creek of river Mithi at the discharge point is duly protected. Because of the construction or any other reason the flow of river Mithi should not be adversely affected," it said.

The judgement came on the plea filed by NGOs Jalbiradari and Vanashakti which challenged the CRZ clearance granted for construction of retaining walls, service road, re-location of Bharat Nagar Police chowki along the banks of Mithi by MMRDA.

It had also sought direction to issue prohibitory orders to Ministry of Environment and Forests from carrying out blasting operations in the river.

(Only the headline and picture of this report may have been reworked by the Business Standard staff; the rest of the content is auto-generated from a syndicated feed.)

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Jun 02 2016 | 4:32 PM IST

Next Story