Around 489 road projects delayed due to land and clearance issues: Gadkari

Union Road Transport and Highways Minister Nitin Gadkari, in a written reply to the Rajya Sabha, said the government is making all efforts to resolve the pending issues

Nitin Gadkari, Nitin, Gadkari
If projects are inordinately delayed due to some reasons and further progress under the ongoing contract is not envisaged, the contract is terminated/foreclosed and re-awarded, with or without modification in the project configuration, Gadkari added. (Photo: PTI)
Press Trust of India New Delhi
2 min read Last Updated : Jul 30 2025 | 4:17 PM IST

As many as 489 road projects, which were originally scheduled for completion by March 2025, are pending due to delays in land acquisition, forest/wildlife clearances and railway approvals, Parliament was informed on Wednesday.

Union Road Transport and Highways Minister Nitin Gadkari, in a written reply to the Rajya Sabha, said the government is making all efforts to resolve the pending issues in close coordination with state governments and other stakeholders to complete these projects.

Gadkari said cost overrun has been incurred in some of the delayed projects due to various factors like enhanced cost of compensation for land and structures, price escalation, Goods & Services Tax (GST) impact, additional VUPs/PUPs on public demand or otherwise, change in General Arrangement Drawing (GAD)/design for Road Over Bridges/Road Under Bridges (ROBs/RUBs) to meet the Railway standards, etc.

If projects are inordinately delayed due to some reasons and further progress under the ongoing contract is not envisaged, the contract is terminated/foreclosed and re-awarded, with or without modification in the project configuration, he added.

Responding to a separate question, Gadkari said national highways are constructed in accordance with specifications of Indian Road Congress (IRC).

"The maximum design speed specified for construction of national highways in different terrains is 120 km/h for expressways and 100 km/h for national highways," he said.

(Only the headline and picture of this report may have been reworked by the Business Standard staff; the rest of the content is auto-generated from a syndicated feed.)

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

Topics :Nitin Gadkariroad projectslandRajya Sabha

First Published: Jul 30 2025 | 4:17 PM IST

Next Story