OpenAI pitched White House on need of massive 5GW data center buildout

OpenAI said investing in these facilities would result in tens of thousands of new jobs, boost the gross domestic product and ensure the US can maintain its lead in AI development

Sam Altman
The push comes as power projects in the US are facing delays due to long wait times to connect to grids, permitting delays, supply chain issues and labor shortages. But energy executives have said powering even a single 5 gigawatt data center would b
Bloomberg
4 min read Last Updated : Sep 25 2024 | 8:36 AM IST
By Shirin Ghaffary

OpenAI has pitched the Biden administration on the need for massive data centers that could each use as much power as entire cities, framing the unprecedented expansion as necessary to develop more advanced artificial intelligence models and compete with China. 
 
Following a recent meeting at the White House, which was attended by OpenAI Chief Executive Officer Sam Altman and other tech leaders, the startup shared a document with government officials outlining the economic and national security benefits of building 5 gigawatt data centers in various US states, based on an analysis the company engaged with outside experts on. To put that in context, 5 GW is roughly the equivalent of five nuclear reactors, or enough to power almost 3 million homes.

OpenAI said investing in these facilities would result in tens of thousands of new jobs, boost the gross domestic product and ensure the US can maintain its lead in AI development, according to the document, which was viewed by Bloomberg News. To achieve that, however, the US needs policies that support greater data center capacity, the document said.

Altman has spent much of this year trying to form a global coalition of investors to fund the costly physical infrastructure required to support rapid AI development, while also working to secure the US government’s blessing for the project. But the details on the energy capacity of the data centers Altman and OpenAI are calling for have not previously been reported. 

“OpenAI is actively working to strengthen AI infrastructure in the US, which we believe is critical to keeping America at the forefront of global innovation, boosting reindustrialization across the country, and making AI’s benefits accessible to everyone,” a spokesperson for OpenAI said in a statement provided to Bloomberg News. 

The push comes as power projects in the US are facing delays due to long wait times to connect to grids, permitting delays, supply chain issues and labor shortages. But energy executives have said powering even a single 5 gigawatt data center would be a challenge. 

Joe Dominguez, CEO of Constellation Energy Corp., said he has heard Altman is talking about building 5 to 7 data centers that are each 5 GW. The document shared with the White House does not provide a specific number. OpenAI’s aim is to focus on a single data center to start, but with plans to potentially expand from there, according to a person familiar with the matter.

“Whatever we’re talking about is not only something that’s never been done, but I don’t believe it’s feasible as an engineer, as somebody who grew up in this,” Dominguez told Bloomberg News. “It’s certainly not possible under a timeframe that’s going to address national security and timing.”

The US has a total of 96 GW of installed capacity of nuclear power. Last week, OpenAI’s biggest investor, Microsoft Corp., struck a deal with Constellation in which the nuclear provider will restart the shuttered Three Mile Island facility solely to provide Microsoft with nuclear power for two decades.

In June, John Ketchum, CEO of NextEra Energy Inc, said the clean-energy giant had received requests from some tech companies to find sites that can support 5 GW of demand, without naming any specific firms. “Think about that. That’s the size of powering the city of Miami,” he said.

That much power would require a mix of new wind and solar farms, battery storage and a connection to the grid, Ketchum said. He added that finding a site that could accommodate 5 GW would take some work, but there are places in the US that can fit one gigawatt.

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

Topics :Artificial intelligenceUSA democracyJobs in Manufacturing

First Published: Sep 25 2024 | 8:34 AM IST

Next Story