GMR commissions 3rd unit of Kamalanga power project

Group's total power generation capacity reaches 2,485 Mw

BS Reporter Bhubaneswar
Last Updated : Mar 25 2014 | 10:03 PM IST
The third unit of GMR Group’s coal-based power plant having 350 Mw capacity at Kamalanga in Dhenkanal district was declared commercially operational today, taking the total output of the plant to 1050 Mw.

The project’s first unit of 350 Mw was commissioned in April, 2013, and the second unit of similar capacity was added in November 2013. With the new capacity addition, total power generation of  GMR Group has touched 2,485.6 Mw, the company said.

Bangalore-headquartered company, with interests in airports, energy, highways and urban infrastructure is establishing the 1,400 Mw project in Odisha under the banner of GMR Kamalanga Energy Limited (GKEL) in two phases of 3x350 Mw and 1x350 Mw, respectively. The firm would supply power to Odisha, Bihar, Haryana and other parts of the country. “With commissioning of all the three units of 350 Mw each, we have completed the first phase of the project. We will begin work on the second and final phase of the project very soon,” said R.V. Sheshan, Managing Director of GKEL,

The Odisha project is being implemented on multiple packages concept and is the third project with Independent Power Producer (IPP) status to have started generation in the state after Sterlite Energy and Arati Power.

The company had signed an agreement with the Odisha government in June, 2006, to establish the power project. As per the agreement, the company has to sell at least 12 per of total power to the state grid at variable cost, which is linked to coal prices.

Besides, it had signed agreements with Haryana state power distribution companies for supply of 350 Mw and Bihar State Electricity Board for supply of 260 Mw.

The company was allocated Rampia coal block jointly with Lanco Group Ltd, Sterlite Energy Ltd, ArcelorMittal India Ltd, Reliance Infrastructure Ltd and Navabharat Power Ltd.

However, the Union coal ministry last month de-allocated the block for slow progress in achieving key milestones necessary for coal mining. Meanwhile, to run the power plant at Dhenkanal, GMR has signed fuel supply agreement with Coal India subsidiary Mahanadi Coalfields Ltd (MCL).

Though the company had earlier announced to establish three units of 350 Mw each at Kamalanga, it later decided to add one more unit of 350 Mw in its second phase expansion.
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Mar 25 2014 | 8:26 PM IST

Next Story