Lakhwar-Vyasi hydel project in U'khand runs into delays

Image
Shishir Prashant New Delhi/ Dehra Dun
Last Updated : Jan 20 2013 | 10:39 PM IST

Cost overrun and inordinate delays have plagued the construction of the 420-Mw Lakhwar-Vyasi multi-purpose hydel project on the river Yamuna near Dakpathar, 50 km from here.

In the 1970s, the dam’s cost was estimated to be around Rs 141 crore only. It has now increased to Rs 4,000 crore with the state government awarding the project to Uttarakhand Jal Vidyut Nigam Ltd (UJVNL) last year.

The real worry for UJVNL is the project’s liabilities as various works were carried out in the past by different players like NHPC and Jaypee Group.

According to the new annual report (2008-09) of the state irrigation department, an amount of Rs 247.64 crore has already been spent on the project that is still to see light of the day.

The construction of the project began in 1979 and came to a halt in 1997 mainly owing to inadequate funds.

NHPC has already sought a claim of Rs 75 crore from UJVNL for preparing the detailed project report (DPR) and other works of the project.

NHPC Executive Director Shart Sharma said he had already sent a letter to UJVNL seeking a claim of Rs 75 crore.

“We have done various works on Lakhwar-Vyasi. Now we want our claim back,” said Sharma.

The Uttarakhand government awarded the multi-purpose Lakhwar-Vyasi hydel project to UJVNL from NHPC last year soon after the two other key projects — 380-Mw Bhaironghati and 480-Mw Palamaneri over Bhagirathi river — were put on hold following protests by environmentalist G D Agrawal.

The state government’s contention is that the Lakhwar-Vyasi was allotted to UJVNL mainly because the state can retain all the power. The project is likely to produce 852 million units of power besides irrigating 40,000 hectares through east Yamuna canal.

Uttar Pradesh, Haryana and Delhi would be the beneficiary states that will get drinking and irrigation water from the project.

Besides, the project would help in generating 75 million units of extra power from downstream projects like Kulhal, Dhalipur and Dhakrani during the lean period by virtue of its vast reservoir.

When contacted, UJVNL Chairman Yogendra Prasad said the company was ready to pay back financial obligations provided the audited accounts were made available regarding various expenditures on the project.

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Aug 19 2009 | 12:31 AM IST

Next Story