NHPC to miss Plan period capacity target by 30%

Image
Sudheer Pal Singh New Delhi
Last Updated : Jan 20 2013 | 12:15 AM IST

However, annual target of generating 17,200 Mw to be met

NHPC Ltd, the country’s largest hydro power producer, is likely to miss its generation capacity addition target of 5,322 Mw for the current Plan period (2007-12) by over 30 per cent owing to geological and law & order problems at project sites. The company will, however, manage to meet its annual commitment of generating 17,200 million units this year.

“We will be able to add around 3,500 Mw by the end of this Plan period. Addition of roughly 2,000 Mw will slip to the next Plan,” said S K Garg, CMD, Miniratna PSU.

The projects which are set to slip to the 12th Plan period include the 800-Mw Parbati II hydro electric project in Himachal Pradesh (originally planned to be commissioned in the current financial year) and five units of 250 Mw each of the 2,000-Mw Lower Subansiri hydro electric project in Arunachal Pradesh (which was to be commissioned in 2010-11).

While the company had managed to add two projects of over 1,000 Mw capacity in the first year of the Plan period, no capacity was added last year. In 2009-10, the company is hopeful of commissioning one of the two targeted projects.

“We would be able to commission the Sewa II project in January 2010,” Garg said. The project was originally scheduled to be commissioned in 2007-08. Six projects of NHPC are slated to come up next year with two more expected to be commissioned in the terminal year of the current Plan period.

India has a hydro power generation capacity of over 36,000 Mw — around a fourth of its total installed capacity. NHPC accounts for over 15 per cent of this hydro generation capacity.

The company, formerly known as the National Hydroelectric Power Corporation Ltd, has planned to invest over Rs 21,600 crore in 12 projects by the end of the current Plan period. It had launched its initial public offer (IPO) earlier this year to raise Rs 6,000 crore from the market. The IPO consisted of a fresh issue of 112 crore equity shares by NHPC and an offer of 56 crore equity shares by the government.

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Oct 25 2009 | 12:41 AM IST

Next Story