UAIL unable to transport alumina pending rail link permission

Company hopes permission for the 13-km long track will come by month end

Hrusikesh Mohanty Berhampur
Last Updated : Oct 09 2013 | 8:51 PM IST
The Hindalco group company, Utkal Alumina International Limited (UAIL), which started alumina production from its plant in south Odisha about four months ago, is unable to transport the material to its end use plants pending permission from the railway authorities to operate the rail link.

“About 13-km-long railway track from the plant site at Tikiri to Deragada in south Odisha’s Rayagada district has already been completed. The company is waiting for the permission from the railway authorities to operate the line. The permission is likely to come by the end of this month” said a company official.

In the absence of transport facility, alumina produced in the plant are being stocked near the plant site.

The powdery material which is converted into aluminium in 2:1 ratio through the smelting process are destined to be sent to Hidalco’s two upcoming smelter plants at Lapanga in Odisha and Mahan in Madhya Pradesh, which are nearing completion, sources said.

Meanwhile, 1.5 million tonne capacity Tikiri refinery of UAIL, which is currently under the stabilisation process, is operating at a low capacity of 25 to 30 percent. It has produced around 30,000 tonnes of alumina so far. The plant will take another six months to reach the full capacity, said a senior officer of the company.

After facing delays of over two decades due to protracted agitations over land acquisition and environment issues, UAIL started its trial production in June, this year. The alumina refinery is powered by a 90 Mw co-generation plant. Its captive bauxite mine, located at Baphilimali on Rayagada and Kalahandi district border, has capacity to produce 4.2 million tonne bauxite per annum. The mine is located about 17-km from the plant site. Before commencing its mining operation, the company had procured some raw material from its captive mine in Madhya Pradesh for the trial production. ‘Raw material is not a problem for us. Around 4 lakh tonnes of bauxite have been raised from the captive mine in last four months”, he said.

UAIL has invested about Rs 7000-crore in the refinery project. Worried over the delay in implementation of the project, two of its original promoters, Tata Sons and Norsk Hydro had pulled out of the project earlier, while another foreign partner, Alcan, had also sold its stake in 2007.
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Oct 09 2013 | 8:12 PM IST

Next Story