Tata Power Renewable Energy had moved the HC challenging the RfS and PPA issued by the Andhra Pradesh Green Energy Corporation (APGECL) in January 2021.
Adani Green Energy (AGEL) in February won five mega solar power projects of 600 megawatt (Mw) each under the tender. State-owned NTPC won 600 Mw in the auction, quoting the lowest tariff of Rs 2.48 per kWh (unit). The lowest tariff discovered in the whole auction process was Rs 2.47 a unit by Torrent Power for a 300 Mw solar project. The award of tender was put on hold.
Sources said the bidding process might undergo revision as both the RfS and PPA were quashed. A copy of the order was not available till the time of going to press. “The High Court has now advised the government of Andhra Pradesh that in case it wishes to procure power, the bidding documents must be in accordance with the Act as well as the guidelines framed thereunder and in case of any deviation, such deviations must be approved by APERC,” said a senior lawyer.
Industry sources said the PPA by APGECL mentioned that any dispute regarding the project would be settled by the state government, as against the legal requirement of moving the state or central electricity regulator. The APGECL had continued with the tendering process despite the legal challenge.
Shri Venkatesh, SKV Law Offices representing Tata Power said, "Electricity Act, 2003 is a complete code and issues such as competitive bidding must be in terms of Act and the Regulator has an intrinsic role to play in such transactions. In this case however, AP had carved out a method outside the Act and also outside the scope and powers of Regulator, which in our view is not permissible. This is what has been held by the Hon'ble High Court as well."
The grid connected power is to be generated at 10 solar parks in Andhra Pradesh under the tender. The plants are planned to be built in the districts of Kurnool, Ananthapuramu, Prakasam, and Kadapa.
The tender received significant investor interest despite the state government cancelling all prior renewable energy contracts in 2019, citing high tariff and malafide intentions. Close to 10 Gw of solar and wind power projects in the state were hit by this decision.
One subscription. Two world-class reads.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app
)