Cost of 1,424 Central infra projects surges 17% to Rs 2,134 crore on delays

Of these projects, 444 are major ones with investment size exceeding Rs 1,000 cr; their cost constitutes 80% of the envisaged outlay

infrastructure
Illustration by Ajay Mohanty
Jayajit Dash Bhubaneswar
2 min read Last Updated : Apr 22 2019 | 8:06 PM IST
The cost of 1,424 Central government infrastructure projects across the country has spiked by 17.4 per cent owing to delays in implementation.

The cost of the projects has surged from Rs 1,817 crore estimated initially to Rs 2,134 crore on account of time overruns. Data sourced from the Ministry of Statistics & Programme Implementation shows 37.8 per cent of the anticipated cost or Rs 8.07 billion has been already incurred.

Of the total pool of 1,424 projects, 444 are major ones with investment size exceeding Rs 1,000 crore. Their combined cost constitutes 80 per cent of the envisaged outlay.

The power, roads, railways and petroleum sectors had the maximum number of completed projects. Eighty five of the 101 projects in these sectors were commissioned by the end of December 2018. 

“Delayed (projects) or  projects  without a definitive timeline  of completion make up  almost 75 per cent  of  the  total  projects  under implementation.  A total of 384 projects are delayed and 686 have no definitive timeline of implementation,” a report by CARE Ratings noted.

The report says there are 686 projects sans any definitive timeline. They are yet to report timelines or status of completion. They have little or no cumulative expenditure and their costs are taken into consideration while estimating  the total cost of outstanding projects. The list includes 607  projects with no date of commissioning and 79 which only have tentative date of completion.

Projects worth Rs 448 crore, or 21 per cent of the total envisaged outlay, have more than one state as beneficiary. They have been categorized under multi-state projects. Maharashtra continues to top the list of beneficiary states, accounting for 9.3 per cent of projects by value being implemented in the country.

According the CARE Ratings report, the pace of implementation of projects has improved considerably through 2018-19. The 2019 elections proved to a major driver in accelerating the rate of execution. The report advocates higher fund outlay for roads, railways, petroleum and coal to meet residual expenditure cost worth Rs 1,020 crore. For these four sectors, the cumulative expenditure incurred continues to be in the range of 25-35 per cent.

One subscription. Two world-class reads.

Already subscribed? Log in

Subscribe to read the full story →
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

Next Story