MahaVitaran has a power purchase agreement with the Tata Power arm, Coastal Gujarat Power Ltd (CGPL), for 760 Mw. In its petition to the Appellate Tribunal for Electricity (ATE), it has asked for modification or setting aside the CERC order, issued in February.
MahaVitaran says it will have to bear an annual burden of Rs 300 crore from CERC’s order.
The CERC order was based on a petition by CGPL seeking relief as the company had pleaded that due to changes made by Indonesia in its coal and mining regulations, the prices of coal had increased, leading to a rise in rates.
CERC asked power procuring utilities, including MahaVitaran, to pay an extra compensation of Rs 329 crore for the period from April 1, 2012, to March 31, 2013, to CGPL. Besides, the distribution utilities were asked to pay a compensatory extra rate of Rs 0.524 a unit from beyond April 1, 2013. Apart from Maharashtra, other states attached are Gujarat (1,805 Mw), Punjab (475 Mw) and Haryana (380 Mw). Business Standard had reported on March 20 about MahaVitaran’s move to approach ATE.
Referring to CERC’s direction to CGPL to contribute one per cent of the return on equity (ROE) based on equity investment, MahaVitaran said the percentage of sharing of ROE needs to be increased, as equivalent sacrifice by the developer needs to be considered. The highest possible ROE should be passed to the procurers.
“This is necessary as during hard times, when procurers are supporting CGPL, eventually, it is necessary that when the latter makes profit, the efforts of procurers may be recognised and the profits shared,” MahaVitaran added.
Further, MahaVitaran insisted the burden of compensatory rates be shared by all stakeholders, including lenders. According to MahaVitaran, lenders should explore all options, including reduction of interest rates, moratorium on principal payment and elongation of loan repayment tenor to reduce the burden of compensatory rates on the procurers. Domestic lenders could, with CERC’s support, approach Reserve Bank of India for forbearance from the ambit of restructuring guidelines, for reduction of interest rate and elongation of loan tenor for the Mundra UMPP.
Additionally, MahaVitaran says CERC should have decided the ceiling rate or the methodology to fix the cap on compensation rates. Such issues cannot be subject to mutual discussion.
On the recovery of past losses of Rs 329 crore for 2012-13 by CGPL, it said the year’s financial accounts had already been audited and finalised. It would be difficult for recovery from consumers for previous periods.
“Matters which have attained finality having rate implications cannot be left to individual negotiations and should have been decided by the regulator with certainty. If the generator is allowed to recover past losses, then a prudence check is required to be carried out to identify such carpet coal cost which needs to be adjusted against the past losses,” MahaVitaran said.
MahaViataran has appealed to the ATE to direct the state electricity regulatory commission to allow it to recover additional compensatory charges from consumers as a direct passthrough.
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app
)