The National Highways Authority of India (NHAI) has been told to work on awarding contracts for around 100 projects, covering 11,151 km, over the financial year starting April 1.
On an average, NHAI would have to award eight projects every month. “We have prepared a tentative list, which we will be awarding in the next financial year. Awarding these should not be an issue,” said a senior NHAI official, who did not want to be identified.
Of the 100 projects, 15 are under the third phase of the National Highways Development Programme, 57 under the fourth phase and 27 under the fifth phase. One project to be awarded in the next financial year is under the South Asian Regional Development Programme – North East.
The award of road projects had slowed during the first tenure of the UPA government. Though one reason was the economic slowdown and the ensuing liquidity crunch, which kept companies away, there was also dissatisfaction with the performance of then road transport minister T R Baalu. At the start of UPA-II in mid-2009, Kamal Nath was brought in to reform the functioning of the ministry and NHAI; he had set a target to build roads at 20 km a day, increasing it from the earlier pace of around three km a day.
Nath also came up with work plans for two financial years, setting a target of awarding a little over 200 projects with a value of over Rs 2 lakh crore in the two financial years ending March 2011. According to the first work plan, NHAI was to award 122 projects covering around 12,000 km by the end of 2009-10 and 96 projects by the end of 2010-11. NHAI was able to award only a little over 70 projects, with the result that the 20-km target remainedon paper.
Now comes the new focus under a new minister, C P Joshi. Industry sources feel awarding these many projects in 12 months will not be difficult, as various other changes in the norms will help. NHAI recently decided to make the bidding process less complex by making one Request for Qualification (RFQ) document valid for a year. With this, road developers would save the six months of time that goes in preparing for the document every time one goes for the bidding.
The ministry has also decided not to award projects on the annuity mode of building roads but on engineering-procurement-construction.
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app