Overflowing tank cause of new leak at Fukushima

At least 430 litres spilled when workers overfilled a storage tank without a gauge

Image
APPTI Tokyo
Last Updated : Oct 03 2013 | 3:47 PM IST
Another day, another radioactive-water spill. The operator of the meltdown-plagued Fukushima Dai-ichi nuclear plant says at least 430 litres (110 gallons) spilled when workers overfilled a storage tank without a gauge that could have warned them of the danger.

The amount is tiny compared to the untold thousands of tons of radioactive water that have leaked, much of it into the Pacific Ocean, since a massive earthquake and tsunami wrecked the plant in 2011.

But the error is one of many the operator has committed as it struggles to manage a seemingly endless, tainted flow.

Also Read

Plant operator Tokyo Electric Power Co. Said today workers detected the water spilling from the top of one large tank when they were patrolling the site the night before.

The tank is one of about 1,000 erected on the grounds around the plant to hold water used to cool the melted nuclear fuel in the broken reactors.

TEPCO said the water then spilled out of a concrete barrier surrounding the tank and believed that most of it reached the sea via a ditch next to the river.

The company later said, however, sea water samples taken just off the plant's coast remained below detectable levels.

The new leak is sure to add to public concern and criticism of TEPCO and the government for their handling of the nuclear crisis.

In August, the utility reported a 300-ton leak from another storage tank, one of a string of leaks in recent months.

That came after the utility and the government acknowledged that contaminated groundwater was seeping into ocean at a rate of 300 tons a day for some time.

TEPCO spokesman Masayuki Ono told an urgent news conference Thursday that the overflow occurred at a 450-ton tank without a water gauge and standing on an unlevel ground, slightly tilting toward the sea.

The tank was already nearly full, but workers pumped in more contaminated water into it to maximise capacity as the plant was facing a serious storage crunch.

Recent rainstorms that flooded tank yards and the subsequent need to pump up and store contaminated rainwater also added to the shortage, he said.

"We could have, and should have, prevented the overflow," he said.

Chief Cabinet Secretary Yoshihide Suga said efforts to stop leaks were still insufficient, but defended TEPCO for detecting the problem more quickly than the last time.

TEPCO said the tank and four others in the same area were already filled up to 98 per cent of its designed capacity, as in many other tanks elsewhere on the plant.
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Oct 03 2013 | 3:40 PM IST

Next Story