Barrick fined USD 16m for Pascua-Lama violations

Image
AP Vallenar (Chile)
Last Updated : May 25 2013 | 5:16 AM IST
Chile's environmental regulator has blocked Barrick Gold Corp's USD 8.5 billion Pascua-Lama project and imposed its maximum fine on the world's largest gold miner, citing "very serious" violations of its environmental permit as well as a failure by the company to accurately describe what it had done wrong.
After a four-month investigation, the Environmental Superintendent said yesterday all other construction work on Pascua-Lama must stop until Barrick builds the systems it promised to put in place beforehand for containing contaminated water.
The fines add up to 8 billion pesos about USD 16 million the highest possible under Chilean law.
Chile's regulator noted that while Barrick itself reported failures, a separate and intensive investigation already begun by the agency's own inspectors found that the company wasn't telling the full truth.
"We found that the acts described weren't correct, truthful or provable. And there were other failures of Pascua Lama's environmental permit as well," said the superintendent, Juan Carlos Monckeberg. "This the first sanction taken by this superintendency and it is the biggest one taken in the environmental history of this country."
Barrick said it accepts all aspects of the resolution.
"We deeply regret that Pascua Lama has suffered inconveniences in its construction and we'll do our best efforts to straighten the road ahead and meet the conditions stipulated in the approved project," said Eduardo Flores Zelaya, president of Barrick South America and Senior Vice President of Pascua Lama. "We respect the institutions of the countries where we operate therefore we will act according to the resolution."
Argentine authorities have insisted that Lama, their side of the bi-national project, will proceed with or without Chile, taking advantage of the infrastructure already in place for its Veladero mine, which is already producing ore just downhill.
But most of Pascua-Lama's 18 million ounces of gold and 676 million ounces of silver are in Chile, where Barrick warned shareholders earlier this year that it might abandon the project if production can't begin in 2013.
Monckeberg said the sanctions, the first since his agency gained enforcement power in December, were based on a thorough investigation by agency inspectors as well as government experts in mining, farming, and water.
Pascua Lama was temporarily halted last month by an appeals court in the northern city of Copiapo after members of the Diaguita indigenous community complained that the project threatens their water supply and pollutes glaciers.
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: May 25 2013 | 5:16 AM IST

Next Story