Efforts on to restore Mumbai-Pune rail link by Aug 16: CR

Image
Press Trust of India Mumbai
Last Updated : Aug 13 2019 | 8:40 PM IST

Nearly 200 workers along with a large number of railway staff are working round-the-clock to restore the Mumbai-Pune rail link, disrupted for more than a week now, by August 16, officials said on Tuesday.

The rail traffic remained suspended for the ninth consecutive day on Tuesday between Lonavala and Karjat in the South-East hilly section of the busy route.

The tracks on the Lonavala-Karjat section were badly damaged following several cases of landslides and boulder- falling due to incessant and heavy rains last month.

Since then, the Central Railway (CR) has suspended train movement on all the three lines on the Karjat-Lonavala ghat section.

CR authorities are carrying out repairs on the affected section in the Khandala area where tracks, overhead equipment as well as signaling system were washed away due to heavy downpour and subsequent landslides, the official said.

According to a senior CR official, 200 workers along with railway staff and supervisors are working round-the-clock to restore traffic on the route braving heavy rains in the ghat section.

CR's chief spokesperson Sunil Udasi said multiple teams of engineers and employees as well as workers are striving hard to restore train services by August 16.

On Saturday, CR's General Manager A K Gupta had personally inspected the restoration work and lauded the officials and workers for their efforts.

Officials from the Research Designs and Standards Organisation (RDSO) - a Railways body - along with other wings of the national transporter were present during Gupta's inspection.

Udasi, who was also present at the site, described the restoration work as "full of challenges".

"Inaccessible area, steep and dangerous slopes, adverse circumstances such as incessant rains, were posing challenges while carrying out the restoration work. Still the restoration and re-railing work was on in full swing," he said.

According to another senior CR official, the restoration work was not merely limited to repairing the tracks, signaling system as well as removal of the debris.

CR officials are also ensuring to avoid any damage to the tracks and signaling system from possible landslides in the coming days, he said.

Disclaimer: No Business Standard Journalist was involved in creation of this content

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Aug 13 2019 | 8:40 PM IST

Next Story