Indian Railways to lay 7 km tracks per day in 2016-17

This is against an average of 4.3 km per day in last six years and part of its capacity augmentation plan

Railway workers at New Delhi Railway Station on Thursday, February 26 2015 Picture by PTI
Railway workers at New Delhi Railway Station on Thursday, February 26 2015 <b>Picture by PTI</b>
Press Trust of India New Delhi
Last Updated : Feb 28 2016 | 3:09 PM IST
Indian Railways will lay 7 km of tracks every day in 2016-17 as against an average of 4.3 km per day in the last six years, as part of its capacity augmentation plan.

The drive is expected to gather further pace in 2017-18 when rails will be laid in about 13 km every day. The bar will be raised further in 2018-19 to 19 km per day, according to an action plan formulated by the public sector behemoth to bolster rail network, Railway Ministry sources said.

Laying new tracks, replacing old ones and doubling and tripling of lines are essential to clearing the traffic bottlenecks, said a senior Railway Ministry official.

Traffic congestion is becoming a bane for freight movement, railways' major source of earning, with goods trains not getting path on priority basis.

Railways is poised to surpass the ambitious target of commissioning 2,500 km broad gauge lines in the current fiscal, 30 per cent more than the last year. According to the official, 2,800 km of tracks will be commissioned next year.

In order to augment freight traffic, there will be three new Dedicated Freight Corridors (DFC) to ensure speedy movement of goods. While North-South DFC is being planned to connect Delhi to Chennai, East-West DFC will link Kharagpur with Mumbai and East Coast DFC will connect Kharagpur to Vijayawada.

These three additional DFC will be funded through innovative financing mechanism including PPP. Railways has already done a feasibility study for these three corridors.

Currently, work is going on Western and Eastern DFC. While Western corridor is being funded by Japan, the Eastern is World Bank funded. Both Western and Eastern corridors will be electrified routes. The public transporter is currently laying tracks in 3,342 km in Eastern and Western DFC involving an expenditure of Rs 81,459 crore.

Railways will form a special purpose vehicle for the Mumbai-Ahmedabad high-speed corridor that will be executed with Japanese cooperation. The project will bring new technology for the country.

Railway's share in loadings is expected to go up to 45 per cent from the current 36 per cent with the commissioning of the DFCs.

Sources said the 56 km-long track between Sasaram and Durgavati on the Eastern Dedicated Freight Corridor is going to be commissioned soon after safety clearance.
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Feb 28 2016 | 12:57 PM IST

Next Story