A bench headed by NGT Chairperson Justice Swatanter Kumar directed the officers from Ministries of Environment and Forests (MoEF) and Water Resources (MoWR), Central Pollution Control Board (CPCB), UP pollution control board (UPPCB) and UP Jal Nigam to meet in his court over the release of waste into the river.
"We direct MoEF, MoWR, CPCB, state pollution control board, municipal body concerned to meet in court no. 1 of NGT. All the officers and their counsel have to participate in the meeting and answer our queries," the bench said.
Yesterday, the green tribunal was told by an experts'
panel that the functional sewage treatment plants in the Garhmukteshwar area of UP do not operate as the domestic sewage network is not connected to the main sewerage system.
A three-member committee set up by the NGT had also informed that the Garhmukteshwar stretch of the Ganga should receive special attention as it was the habitat of the critically-endangered Gangetic Dolphin, an indicator species for the river's ecosystem.
"Unless this is done, we will be in a situation where a sewerage system is in place, the STP has been made operational and yet not a drop of sewage is treated simply because there is lack of connectivity between the different components," it had said, adding there was a need for immediate and time bound action to ensure effecive cleaning of the river.
The committee comprising a Director from Ministry of Water Resources, a scientist from the CPCB and advocate and local commisioner Ritwick Dutta, which was set upto inspect status of sewage treatment plants (STPs) in Garhmukteshwar, had also sought direction to the concerned agencies to present action plan and progress of implementation of programme for the protection of Gangetic Dolphin.
Earlier, the bench had ordered a CBI probe into the execution of the Ganga cleaning project after it noted that Rs 31.82 crore was spent on two STPs and a 58-km long sewerage line project without due analysis and verification of the actual pollution load in the Garh drain and Brijghat drain.
NGT had slammed the state's Jal Nigam for building the STPs on the drains joining Ganga without any survey and said it had wasted Rs 1500 crore since 1987 and still not cleaned "even a single drop" of the river.