"Although the pace of execution increased by 17 per cent during 8M FY2017 (April-November) to 5.82 km/day from 4.96 km/day, during 8M FY2016; it is just 27 per cent of target execution of 21.92 km/day.
"Therefore, in terms of both award and execution, the NHAI is expected to miss the target by a wide margin," the ratings agency said.
The Ministry of Road Transport and Highways (MoRTH) planned to increase both the awards and the execution in FY17 by 2.5 times from that of the FY16 levels. For NHAI, the targets are steep with a target execution of 8,000 km (21.92 km/day) and target awards at 15,000 km.
In August 2016, the Cabinet Committee on Economic Affairs (CCEA) had authorised the NHAI to monetise public funded National Highway projects which are operational and generating toll revenues for at least two years after the Commercial Operations Date through the Toll-Operate-Transfer (TOT) model.
Seventy-five operational national highway projects totalling 4,376 km completed under public funding have been preliminarily identified for potential monetisation, using the TOT model.
For these 75 projects, the median vintage in terms of toll collection track record stood at 5.22 years. Out of these, nearly 26 projects (35 per cent of total) are on BOT (Annuity) basis and the remaining 65 per cent have been implemented on engineering, procurement and construction (EPC) basis.
According to K Ravichandran, Senior Vice President and Head, Corporate Ratings at Icra: "Given the wide variation in toll collections, the attractiveness of certain stretches with long vintage and established traffic volumes - especially the ones along the GQ - is much more when compared to the ones with less operational track record and weak toll collections.
According to ICRA Research's estimates, the total value of 75 projects proposed to be awarded through the TOT is estimated at Rs 356 billion. Assuming the average cost to the NHAI is Rs 0.13 billion per km (for a four-lane project), the proceeds from monetisation through the TOT route can be used towards road construction of around 2,700 km, it added.
Disclaimer: No Business Standard Journalist was involved in creation of this content
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app