With future coal mining projects stuck in delay over acquisition of land and rehabilitation and resettlement (R&R) issues, among others, CIL had applied for environment clearance for one-time production capacity expansion by 50 per cent in existing operations without public hearing.
"Blanket permission for 50 per cent expansion without public hearing under 7(ii) of EIA Notification, 2015, and without capping for sustainable mining cannot be given," an Expert Appraisal Committee (EAC) of the Environment Ministry said after assessing the proposal at a recent meeting.
"While considering any such proposal, a detailed sample study for socio-economic aspects needs to be carried out to assess the extent of impact," EAC noted.
CIL has informed EAC that it's facing hurdles to increase production from future projects to 908 million tonnes in 2019-20 from the existing level of 500 million tonnes.
"The only option left with CIL is to enhance its production from existing and ongoing projects. This will be achieved by advancing project activities and resources without deviating from the environmental norms," it said.
Also, there is a delay in authentication of land and R&R sites by state authorities, exorbitant demand from project affected peoples beyond the norms, delay in obtaining NoC from state authorities as well as handover of forest land, delaying the commissioning of future projects, it reasoned.
CIL also clarified that environment impact of expansion of production by 50 per cent from the existing operations would be confined to only additional dust generation while removal and backfilling of overburden -- the layer of earth above coal seams that has to be dug out before mining coal -- will not be affected.
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app