Norms stringent, cumbersome for getting envrn clearances: NHPC

Image
Press Trust of India New Delhi
Last Updated : Aug 28 2014 | 5:40 PM IST
With many projects stuck, state- owned NHPC has said stringent norms as well as cumbersome procedures are leading to delay in getting environmental and forest clearances.
Besides the hydel power producer has said that land acquisition process for "infrastructure works as well as for project's components, including submergence is quite cumbersome and time consuming".
NHPC's 10 proposed hydel projects, together having generation capacity of 8,800 MW, are awaiting clearances, as per its website.
"Stringent norms and cumbersome procedures for getting Environment clearance, Forest clearance and clearance from National Board for Wild Life (wherever applicable) lead to delay in obtaining clearance of projects, which may adversely affect the capacity addition programme," according to NHPC's annual report for 2013-14 period.
At present, NHPC has an installed capacity of 6,507 MW.
In the last financial year, NHPC saw its net profit after tax drop to Rs 1,218.75 crore from Rs 2,617.41 crore recorded during 2012-13 period.
Apart from clearance hurdles, the utility has said it is facing stiff competition from independent power producers and other competitors in allotment of new projects.
Further, NHPC has said that projects/ power stations located at sensitive border areas witness law & order problems as well.
"Militant and extremist groups of the areas quite often target NHPC, perceiving it to be a government representative... The projects/ power stations located in border areas quite often become reference points for differences in international relations," the report said.
It also noted that many hydro projects may get delayed or abandoned due to inter-state river disputes.
"Water being a state subject, state governments are demanding higher share of free power and other incentives, resulting in higher tariff," the report said.
These are among the factors perceived by the company's management as "threats/ risks/ weaknesses in construction of hydro power projects".
Meanwhile, in his letter to shareholders, that is part of the annual report, NHPC Chairman and Managing Director R S T Sai efforts to diversify into thermal, wind and solar power has started fetching results in India and overseas.
*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

First Published: Aug 28 2014 | 5:40 PM IST

Next Story