The Ministry of New and Renewable Energy (MNRE) has granted an extension of 30 days for commissioning of renewable energy projects beyond the lockdown period.
The renewable energy implementing agencies may grant extension of time for commissioning of such projects, impacted due to coronavirus lockdown, equivalent to the period of lockdown and additional 30 days for normalisation beyond the curb period, the ministry said in a statement on Tuesday.
This will be a blanket extension and there will be no requirement of case to case examination, as also there will be no need to ask for any evidence for extension due to lockdown, it said.
The ministry has also said that all implementing agencies of the MNRE will treat lockdown due to COVID-19, as force majeure.
Referring to the renewable energy departments (including agencies under power/ energy departments of states, but dealing in renewable energy), the ministry has asked them that theymay also treat lockdown due to COVID-19, as force majeure and may consider granting appropriate time extension on account of such lockdown.
The decision was taken after, RE developers represented to the Ministry that they may be granted a general time extension on account of lock down (due to COVID-19) and additional time required for normalization after such lockdown.
The MNRE had, earlier on March20, 2020,issued directions to SECI, NTPC and Additional Chief Secretaries / Principal Secretaries / Secretaries of Power / Energy / Renewable Energy (RE) Departments of state governments/ UTs/ Administrations, to treat delay on account of disruption of the supply chains due to spread of coronavirus in China or any other country, as force majeure.
It also said that they may grant suitable extension of time for projects, on account of coronavirus, based on evidences / documents produced by developers in support of their respective claims of such disruption of the supply chains due to spread of coronavirus in China or any other country.
Disclaimer: No Business Standard Journalist was involved in creation of this content
You’ve reached your limit of {{free_limit}} free articles this month.
Subscribe now for unlimited access.
Already subscribed? Log in
Subscribe to read the full story →
Smart Quarterly
₹900
3 Months
₹300/Month
Smart Essential
₹2,700
1 Year
₹225/Month
Super Saver
₹3,900
2 Years
₹162/Month
Renews automatically, cancel anytime
Here’s what’s included in our digital subscription plans
Exclusive premium stories online
Over 30 premium stories daily, handpicked by our editors


Complimentary Access to The New York Times
News, Games, Cooking, Audio, Wirecutter & The Athletic
Business Standard Epaper
Digital replica of our daily newspaper — with options to read, save, and share


Curated Newsletters
Insights on markets, finance, politics, tech, and more delivered to your inbox
Market Analysis & Investment Insights
In-depth market analysis & insights with access to The Smart Investor


Archives
Repository of articles and publications dating back to 1997
Ad-free Reading
Uninterrupted reading experience with no advertisements


Seamless Access Across All Devices
Access Business Standard across devices — mobile, tablet, or PC, via web or app