Delay in irrigation projects costs Telangana exchequer Rs 1 trn more: CAG

An expenditure of Rs 1,73,564 crore was incurred on these projects as of March 2023

A Revanth Reddy, Revanth
An expenditure of Rs 1,73,564 crore was incurred on these projects as of March 2023. (Photo:PTI)
Press Trust of India Hyderabad
2 min read Last Updated : Aug 03 2024 | 12:22 PM IST

The cost of 20 irrigation projects commenced between 1983 and 2018 in Telangana doubled from over Rs 1 lakh crore to Rs 2 lakh crore as on March 2023, due to non-completion, the CAG report has said.

According to the report (for 2022-23) by the Comptroller and Auditor General (CAG) which was placed in the state legislature on Friday, non-completion of projects deprives the state of the intended benefits of economic growth and there was no assurance on returns from the investments in irrigation and flood control as the state government did not disclose financial results of any of the irrigation projects.

"There were 20 incomplete irrigation projects (commenced between 1983 and 2018) to be completed by the year 2023. The original cost of these projects has increased from Rs 1,02,388 crore to Rs 2,06,977 crore i.e., an escalation by Rs 1,04,589 crore (102 per cent)," the auditing watchdog said.

An expenditure of Rs 1,73,564 crore was incurred on these projects as of March 2023. In addition to this, the government has a pending liability of Rs 8,971 crore in respect of 13 incomplete irrigation projects, the report said.

"Inordinate delays in the completion of these projects/works not only keep the financial burden of the government increasing year after year, but also depriving the public of the intended benefits," the CAG report opined.

The CAG also said Hyderabad Urban Agglomeration is a case where there has been no expenditure despite Rs 10,000 crore being proposed in the budget of 2020-21 to carry out Musi River purification and Musi River Front Project, among others, with an estimation that Rs 50,000 crore would be required for next five years ( 2020-21 onwards).

However, the entire provision of Rs 10,000 crore remained unutilised during 2020-21 and the following year (2021-22) the budget was reduced significantly to Rs 2,600 crore and the next year (2022-23) it was further shrank to justice Rs 200 crore even and the reduced provision remained unutilised, the report said.


(Only the headline and picture of this report may have been reworked by the Business Standard staff; the rest of the content is auto-generated from a syndicated feed.)

*Subscribe to Business Standard digital and get complimentary access to The New York Times

Smart Quarterly

₹900

3 Months

₹300/Month

SAVE 25%

Smart Essential

₹2,700

1 Year

₹225/Month

SAVE 46%
*Complimentary New York Times access for the 2nd year will be given after 12 months

Super Saver

₹3,900

2 Years

₹162/Month

Subscribe

Renews automatically, cancel anytime

Here’s what’s included in our digital subscription plans

Exclusive premium stories online

  • Over 30 premium stories daily, handpicked by our editors

Complimentary Access to The New York Times

  • News, Games, Cooking, Audio, Wirecutter & The Athletic

Business Standard Epaper

  • Digital replica of our daily newspaper — with options to read, save, and share

Curated Newsletters

  • Insights on markets, finance, politics, tech, and more delivered to your inbox

Market Analysis & Investment Insights

  • In-depth market analysis & insights with access to The Smart Investor

Archives

  • Repository of articles and publications dating back to 1997

Ad-free Reading

  • Uninterrupted reading experience with no advertisements

Seamless Access Across All Devices

  • Access Business Standard across devices — mobile, tablet, or PC, via web or app

More From This Section

Topics :Irrigation projectsAgriculture MinisterTelangana govt

First Published: Aug 03 2024 | 12:21 PM IST

Next Story