Thermal Power Plants

EPC major Tata Projects Ltd (TPL) on Monday said it has secured an order to build the complete supporting setup for a 1,600 MW coal-fired power plant in Central India. Under the contract, Tata Projects will be responsible for the design, engineering, manufacture, supply, construction, erection, testing, and commissioning of the project's balance-of-plant systems. These systems encompass critical infrastructure required to support reliable plant operations beyond the boiler-turbine-generator island, the company said in a statement. "Tata Projects Ltd (TPL), one of India's leading Engineering, Procurement and Construction (EPC) companies, has been awarded the complete Balance of Plant (BoP) turnkey package for a 2 x 800 MW ultra-supercritical thermal power project in Central India by a leading integrated power utility," the statement said. The project encompasses the complete BoP scope, including coal and biomass handling systems, fuel and ash management facilities, water intake, ..

Updated On: 23 Nov 2026 | 1:41 PM IST

Coal inventories at power plants have stabilised as rake loading and supplies improve, but stocks remain under pressure, with 87 plants reporting critically low levels

Updated On: 12 Oct 2026 | 10:24 PM IST

L&T Energy CarbonLite Solutions has secured a limited notice to proceed for the main plant package of the 1,600 MW Chandrapura thermal power project in Jharkhand.

Updated On: 07 Oct 2026 | 4:22 PM IST

India's coal stocks for the power sector can support around 62 days of consumption as production and dispatch rise amid strong supply growth

Updated On: 06 Aug 2026 | 6:04 PM IST

A robust order pipeline and long-term power-sector expansion support BHEL's growth outlook, but sustained margin gains and timely execution remain critical

Updated On: 09 Jun 2026 | 10:41 PM IST

Adani Group will invest Rs 33,081 crore in Odisha across power, cement and data infrastructure projects, creating nearly 10,000 jobs and supporting the state's long-term economic growth plans

Updated On: 08 Apr 2026 | 9:32 PM IST

Government has long sought to cut coal imports for the power sector, but those efforts have failed as power plants have been unable to burn lower-quality local coal

Updated On: 27 Feb 2026 | 1:57 PM IST

NTPC says flexible and two-shift operations for renewable integration are causing wear and failures in thermal units, prompting the power ministry to review plant stress and grid needs

Updated On: 20 Feb 2026 | 10:49 PM IST

The coal-based Nabha power plant houses two supercritical units of 700 Megawatt capacity each at Rajpura in Patiala district, Punjab

Updated On: 16 Feb 2026 | 10:50 PM IST

The Association of Power Producers (APP) on Thursday said the inability of several thermal power plants to meet biomass co-firing targets in FY 202425 was primarily due to limited biomass availability and technical constraints -- not a lack of intent or effort by generators. This comes after the Commission for Air Quality Management (CAQM) issued show-cause notices to six thermal power stations within a 300-km radius of Delhi and proposed environmental compensation of Rs 61.85 crore for the reported shortfall, the Association said in a statement. APP noted that the domestic market for torrefied biomass pellets -- mandated for plants equipped with ball and tube mills -- remains significantly underdeveloped. The industry continues to face challenges such as insufficient supplier capacity, high rejection rates due to moisture or volatile matter, and the absence of OEM-validated solutions, it stated. It cited the example of Talwandi Sabo Power Ltd (TSPL), a 1,980-MW plant in Punjab, wh

Updated On: 25 Dec 2025 | 2:44 PM IST

Adani Power Ltd (APL) would invest around Rs 48,000 crore to set up a greenfield power plant while Adani Green Energy Ltd (AGEL) would put in approximately Rs 15,000 crore for the two PSPs

Updated On: 14 Nov 2025 | 6:58 PM IST

Coal India and Damodar Valley Corporation have signed a joint venture to set up a Rs 21,000-crore, 1,600 MW thermal power plant at Chandrapura in Jharkhand, expected to start operations by FY32

Updated On: 07 Nov 2025 | 6:37 PM IST

The government has decided to hand over 105 hectares of land belonging to the Korba Thermal Power Station (KTPS) to the industries department, paving the way for the state's first aluminium park

Updated On: 28 Aug 2025 | 4:23 PM IST

Under the previous policy framework, electricity produced using Coal India Ltd's linkage coal could not be traded in the open market, regardless of whether it was surplus

Updated On: 07 Aug 2025 | 5:00 PM IST

The power ministry has planned to develop an additional 97 GW coal and lignite-based electricity generation capacity to achieve the required 307 GW of thermal installed capacity by 2034-35, Parliament was informed on Thursday. This assumes significance in view of India's ambitious target of 500 GW of renewable energy capacity by 2030 and net zero target by 2070. In a written reply to Lok Sabha, Minister of State for Power Shripad Yesso Naik said, "The projected thermal (coal and lignite) capacity requirement by the year 2034-35 is estimated at approximately 3,07,000 MW as against the 2,11,855 MW installed capacity as on March 31, 2023." The minister informed the House that to meet this requirement, the Ministry of Power has envisaged setting up an additional minimum of 97,000 MW of coal and lignite-based thermal capacity. The installed electricity generation capacity in the country is 485 GW as on June 2025. As per the National Electricity Plan (Generation) published in May 2023,

Updated On: 07 Aug 2025 | 2:35 PM IST

The company will supply power from a greenfield 3x800 MW Ultra-supercritical thermal power plant, to be developed under the Design, Build, Finance, Own, and Operate (DBFOO) model

Updated On: 07 Aug 2025 | 10:45 AM IST

The changes to India's policy on emissions from coal plants are not a rollback - but a confident assertion of regulatory maturity, scientific integrity, and rational national interest

Updated On: 17 Jul 2025 | 10:08 PM IST

NTPC mainly runs coal-fired plants and wants to identify ones that can be retired in the next five years, preferably replaced by SMRs

Updated On: 08 Apr 2025 | 10:30 AM IST

Govt expecting 37 mt of coal stocks by Oct-end, 7 mt more than the previous year

Updated On: 03 Apr 2025 | 12:20 AM IST

The project will be part of an expansion plan of the Hasdeo Thermal Power Station (HTPS) located in Korba

Updated On: 02 Apr 2025 | 4:47 PM IST