WebinarsNew
Deep DiveNew
Explore Business Standard
EPC major Tata Projects Ltd (TPL) on Monday said it has secured an order to build the complete supporting setup for a 1,600 MW coal-fired power plant in Central India. Under the contract, Tata Projects will be responsible for the design, engineering, manufacture, supply, construction, erection, testing, and commissioning of the project's balance-of-plant systems. These systems encompass critical infrastructure required to support reliable plant operations beyond the boiler-turbine-generator island, the company said in a statement. "Tata Projects Ltd (TPL), one of India's leading Engineering, Procurement and Construction (EPC) companies, has been awarded the complete Balance of Plant (BoP) turnkey package for a 2 x 800 MW ultra-supercritical thermal power project in Central India by a leading integrated power utility," the statement said. The project encompasses the complete BoP scope, including coal and biomass handling systems, fuel and ash management facilities, water intake, ..
The Association of Power Producers (APP) on Thursday said the inability of several thermal power plants to meet biomass co-firing targets in FY 202425 was primarily due to limited biomass availability and technical constraints -- not a lack of intent or effort by generators. This comes after the Commission for Air Quality Management (CAQM) issued show-cause notices to six thermal power stations within a 300-km radius of Delhi and proposed environmental compensation of Rs 61.85 crore for the reported shortfall, the Association said in a statement. APP noted that the domestic market for torrefied biomass pellets -- mandated for plants equipped with ball and tube mills -- remains significantly underdeveloped. The industry continues to face challenges such as insufficient supplier capacity, high rejection rates due to moisture or volatile matter, and the absence of OEM-validated solutions, it stated. It cited the example of Talwandi Sabo Power Ltd (TSPL), a 1,980-MW plant in Punjab, wh
The power ministry has planned to develop an additional 97 GW coal and lignite-based electricity generation capacity to achieve the required 307 GW of thermal installed capacity by 2034-35, Parliament was informed on Thursday. This assumes significance in view of India's ambitious target of 500 GW of renewable energy capacity by 2030 and net zero target by 2070. In a written reply to Lok Sabha, Minister of State for Power Shripad Yesso Naik said, "The projected thermal (coal and lignite) capacity requirement by the year 2034-35 is estimated at approximately 3,07,000 MW as against the 2,11,855 MW installed capacity as on March 31, 2023." The minister informed the House that to meet this requirement, the Ministry of Power has envisaged setting up an additional minimum of 97,000 MW of coal and lignite-based thermal capacity. The installed electricity generation capacity in the country is 485 GW as on June 2025. As per the National Electricity Plan (Generation) published in May 2023,